Flow mark! Reject the bid! Postponement! Nearly 1GW photovoltaic projects have changed!

2026-01-19 19:17:05

On January 16, the EPC general contractor of Yangquan Distributed Photovoltaic Project in Wulan Town, Etuoke Banner, Inner Mongolia issued a bid announcement, which was due to the fact that less than three bidders submitted bidding documents at the bid opening stage.

On

16 January, Sheep pen, Wulan Town, Etuoke Banner, Inner Mongolia " has been deferred 4 times." The deadline for submission of project bidding documents and the time for bid opening have been extended from 9:30 a.m. on October 22, 2025 to 9: 30 a.m. on January 16, 2026.

" This project is divided into 1 bid section . The content of the bid section is the EPC general contracting of the new 100MW Yangquan Photovoltaic Power Generation Project, including the design, construction, acceptance, handover and other general contracting contents of the project.

In addition to the above projects, there are also a number of projects in the near future, such as flow mark, delay and other abnormal situations.

On January 19, Ganzhou Xingzhiyuan Project Management Co., Ltd. The reason is that the substantive response of the project is less than quorum .

On January 19, Guoneng Ningxiang DC supporting Hongsibao 1.5 million kilowatt new energy base project general contracting (the first tender section)-the second photovoltaic area foundation project tender section project announcement said that. The deadline for submission of response documents for this bid section is changed to 16:00 p.m. on January 23, 2026.

On January 16, Erbil Erbi1125 MWp Photovoltaic Power EPC General Contracting Project issued another extension announcement. It is worth noting that the project has been postponed six times, and the bid closing/opening time has been postponed from 9:00 on September 19, 2025 to 9:00 on January 29, 2026.

On January 16 , CGN Jianhu County, Jiangsu Province Fishing-photovoltaic Complementary Phase II 200 MW Photovoltaic Power Generation Project EPC General Contracting Project issued postpone the bid closing/opening time of the bidding documents. The specific time is to be determined and will be notified 3 working days in advance.

Previously, the closing/opening time of bidding documents for the project was postponed from 9:30 on January 15, 2026 to 9:30 on January 22, 2026.

On January 16 , the roof distributed photovoltaic project of Heyuan Branch Center of Lingnan Modern Agricultural Science and Technology Laboratory in Guangdong Province issued a notice of bid rejection because the number of valid bidders was insufficient. Procurement failed .

On January 14 , the EPC general contracting bidding of roof distributed photovoltaic power generation project (Phase I) of Shanxi Xiangyang Mining Group Co., Ltd. was postponed, and the submission/opening time of bidding documents was postponed to 14:30 on January 30, 2026.

It is understood that the total installed capacity of the project is 12. 02811 MWp (AC side capacity) 10.

On January 13 , the roof distributed photovoltaic power generation project of Licheng Kechuang Center issued a (second) announcement of bid rejection. After the review of the

Bid Evaluation Committee, it is unanimously agreed that the suppliers Fujian Yefeng Electric Power Construction Engineering Co., Ltd., Shenzhen Skyworth Photovoltaic Technology Co., Ltd., Yete Construction Co., Ltd. and Xiamen Branch of Zhengneng (Fujian) Construction Engineering Co., Ltd. fail to substantially respond to the requirements of the bidding documents, and the technical compliance review is not passed, which will be regarded as invalid bidding. As there are less than 3 valid bidders, the bid of this project is rejected according to law. On the day of bid

rejection, the project immediately issued the third tender announcement of the project. The project is located in Licheng District, Quanzhou City, Fujian Province, and the tenderer is Quanzhou Lijian New Energy Technology Co., Ltd.

On January 12 , the first batch of industrial and commercial 100MW distributed photovoltaic (EPC) projects in Yunnan area of Yunnan Mekong New Energy Development Co., Ltd . The reason for the failure of bidding is that the bidding documents submitted by the bidders have not been received by 14:00 on January 9, 2026, and the tenderee will re-invite tenders according to law.

It is reported that the total investment of the project is 200 million yuan, and the purchaser is Yunnan Mekong New Energy Development Co., Ltd.On December 26 ,

2025, Lingyuan Sihedang 300MWp Centralized Parity Photovoltaic (EPC) Project issued a notice of bid rejection. The announcement shows that the reason for the rejection of the project is that the number of valid bidders is less than statutory three .

Previously, according to Digital New Energy DataBM, the reason for the change of the project was either a major change in the project or less than three response units.

All can be viewed after purchase
Correlation

Domestic concrete price statistics in March showed that the statistics covered many parts of the country. From the overall data, the national concrete price has a slight change, with a ring-to-ring change of 0.02% and a year-on-year change of-10.42%. Prices in some areas remained unchanged during the statistical cycle, with a month-on-month change of 0.00% in Beijing, Tianjin and other places. The change is more obvious in Liaoning, with a ring ratio of 0.37%, while Hainan is only-1.33% year-on-year, and the change is relatively moderate. The range of price changes in different regions shows certain differences.

2026-04-01 11:08:02

What is happening in the cement industry?

2026-03-29 07:02:03

On March 19, the 2026 Anti-monopoly Work Conference was held in Xiamen, Fujian Province. In 2026, we should focus on the construction of a unified national market, deepen the governance of fair competition, standardize the order of market competition, and thoroughly rectify the "involution" competition.

2026-03-19 15:11:30

Mainstream trading center of gravity moved down to about 0.77 yuan/W

2026-03-18 17:43:21

On March 18, the Zhejiang Development and Reform Commission issued the "Notice on Issuing the Implementation Plan of the First Batch of Major Construction Projects in 2026 for Expanding Effective Investment in Zhejiang Province".

2026-03-18 16:59:42

On March 16, the government of Anhui Province issued a list of key projects in 2026.

2026-03-18 09:30:37

From January to February, the added value of industries above scale increased by 6.3% year-on-year (the growth rate of added value is the real growth rate after deducting price factors). On a month-on-month basis, in February, the value added of industries above designated size increased by 0.83% over the previous month.

2026-03-16 11:32:24

What is happening in the cement industry?

2026-03-15 07:02:02

Located in the core of Shanghai Hongqiao International Central Business District, the Enabling Center aims to create a double bridgehead for new energy enterprises to "invite in" and "go out" and a gathering place for the headquarters of new energy enterprises at home and abroad. It was jointly founded by the Global Green Energy Council, the Global Energy Storage and Battery Council, the Asia-Pacific New Energy Industry Association, the Asian Photovoltaic Industry Association and other international organizations, as well as leading enterprises in the field of global photovoltaics and hydrogen storage.

2026-03-13 20:20:40

This week, 5 component manufacturers partially cut prices or release special prices.

2026-03-13 16:01:21

On March 13, Wang Hongzhi, Secretary of the Party Leadership Group and Director of the State Energy Administration, signed an article entitled "Anchoring the Goal of Building a Strong Energy Country and Promoting the Reform of Energy Marketization in the Fifteenth Five-Year Plan Period", which was published in the Learning Times.

2026-03-13 10:01:22

I hope that this book can further promote the common understanding of involution competition and provide reference for anti-involution work in all walks of life in China.

2026-03-10 12:03:19

Wood Mackenzie's latest Lithium Energy Transition Outlook report points out that in the context of accelerated energy transition, global lithium demand may exceed 13 million tons by 2050, more than twice the benchmark forecast. Without significant new investment, a supply gap could emerge as early as 2028.

2026-03-05 17:32:44

On March 3, Zhong Baoshen, deputy to the National People's Congress and chairman of Longji Green Energy, was interviewed by several media and put forward a number of suggestions based on the development status and problems of the photovoltaic industry.

2026-03-05 17:18:58

Domestic concrete price statistics in February show that concrete prices in many parts of the country have changed to varying degrees. The national ring-to-ring ratio decreased by 0.48% and the year-on-year ratio decreased by 11.61%. There is no change in the ring ratio in most regions, among which Jiangsu has a relatively large decline in the ring ratio, while Shaanxi has a certain increase in the ring ratio, which is more prominent in the regions with changes. On a year-on-year basis, various regions also showed a decline in varying degrees, with a relatively large decline in some areas and a relatively small decline in some areas.

2026-03-02 10:14:17

This paper proposes an "atomic-scale interface bonding" technology, which uses atomic layer deposition process to introduce a controllable hafnium oxide (HfOx) intermediate layer into the key interface of the cell, synchronously stabilizes the hole and electron transport interface from the atomic scale, and successfully solves the problem that the efficiency and stability of perovskite solar cells are difficult to improve in coordination, which has long restricted the development of perovskite solar cells.

2026-02-27 10:54:30