The total investment is 200 million yuan! Environmental Impact Assessment of Machine-made Sandstone Project with Annual Output of 10 Million Tons in Hunan Province Approved

2023-03-01 09:23:09

According to the EIA report, the project includes two aggregate production workshops, two raw material storage yards and two finished product storage yards, with a total floor area of 105827. 1 square meters.

Recently, the yuanjiang Branch of the Ecological Environment Bureau of Yiyang City, Hunan Province, made an approval decision on the environmental impact assessment report of Lishan's annual output of 10 million tons of machine-made sand and gravel (Phase I) project and publicized it.

It is reported that the project is located in Baijiagou Village, Nanzui Town, yuanjiang City. The first phase mainly constructs two production lines, one with an annual output of 2.009 million tons of machine-made sand and the other with an annual output of about 5.333 million tons of machine-made sand and about 2.667 million tons of gravel. The project is invested and constructed by Hunan Lishan New Material Technology Co., Ltd., a local private enterprise, with a total investment of 200 million yuan.

According to the EIA report, the project includes two aggregate production workshops, two raw material storage yards and two finished product storage yards, with a total floor area of 105827. 1 square meters. The specific equipment in the production workshop mainly includes drum screen, cone crusher, roller crusher, vibrating screen, transmission system, control system, etc. Both the raw material storage yard and the finished product storage yard are transported by spraying devices and fully enclosed belts.

Among them, the production workshop covers an area of about 2000 square meters, steel frame structure closed plant, the construction of an annual output of 2.009 million tons of machine-made sand production line. The second production workshop covers an area of about 12000 square meters, with a closed steel frame structure, and a production line with an annual output of about 5.333 million tons of machine-made sand and about 2.667 million tons of gravel.

In addition, during the design, construction and operation of the project, the construction unit must fully implement the pollution prevention and ecological protection measures proposed in the Report Form, strictly implement the "three simultaneous" system of environmental protection, and comply with the requirements of standard discharge and clean production.

All can be viewed after purchase
Correlation

It mainly constructs a pebble sand production line with an annual output of 4.5 million and a sand and gravel distribution center with an annual throughput of 9.7 million tons.

2023-06-26 09:43:10

The project is located in Xiaofanzhou Village, Canggang Town, Hanshou County, Changde City, Hunan Province, on the right bank of yuanshui Branch, which can sail with ships of more than 2000 tons all the year round, and the water transportation is very convenient.

2023-03-20 09:25:42

According to the EIA report, the project includes two aggregate production workshops, two raw material storage yards and two finished product storage yards, with a total floor area of 105827. 1 square meters.

2023-03-01 09:23:09

On the morning of December 29, the machine-made sand project in Canggang Town, Hanshou County, Changde City, Hunan Province was officially started.

2023-01-04 09:16:12

Prices in Ningxia are stable but export sales are low, Gansu is facing callback pressure after price increases, sales in Qinghai are not up to expectations after pushing up, Shaanxi has great resistance to price recovery, Xinjiang is stable due to engineering demand, and the overall market is mainly stable price wait-and-see in the short term.