Latest Progress of Longji 8.6G W Reconstruction and Expansion Component Project!

2025-06-26 09:52:48

On June 20, the Bureau of Ecology and Environment of Jiaxing City, Zhejiang Province, announced the approval decision on the EIA document of Jiaxing Longji Photovoltaic 8.6G W Single Crystal Module Reconstruction and Expansion Project.

On June 20, the Bureau of Ecology and Environment of Jiaxing City, Zhejiang Province, announced the approval decision on the EIA document of Jiaxing Longji Photovoltaic 8.6G W Single Crystal Module Reconstruction and Expansion Project .

It is reported that the total investment of the project is 257.79 million yuan , including 500,000 yuan for environmental protection. The construction site is located on the east side of Baiyunqiao Road and the south side of Jixiang West Road, Wangdian Town, Xiuzhou District, Jiaxing City. Using 17 production lines of existing spare workshops (1 , 3 , 4 # and 6 # workshops) to carry out technical transformation and intelligent upgrading, it is planned to purchase new facilities and equipment such as automatic glue adding equipment, screen printing equipment, scribing welder, overlap welder, junction box AI equipment, battery EPL and so on, and to upgrade typesetting machine, assembly line and other related facilities and equipment. After the completion of the project, the production capacity of monocrystalline modules is expected to increase by 8.6GW . According to

the data, Jiaxing Longji Photovoltaic Technology Co., Ltd. is a wholly-owned subsidiary of Longji Green Energy, and the actual production capacity of monocrystalline modules in 2024 is 9.5G W .


All can be viewed after purchase
Correlation

On June 20, the Bureau of Ecology and Environment of Jiaxing City, Zhejiang Province, announced the approval decision on the EIA document of Jiaxing Longji Photovoltaic 8.6G W Single Crystal Module Reconstruction and Expansion Project.

2025-06-26 09:52:48

On June 22, the front page of Jiangsu Huai'an Daily published an article focusing on the progress of local project construction. The article mentions that the project of Trina Solar Huai'an Base is pushing forward.

2025-06-24 09:39:42

On December 12, Beixin Building Materials issued the resolution announcement of the twenty-fifth interim meeting of the seventh board of directors. The announcement said that the board meeting considered and approved the Bill on the Appointment of Deputy General Manager of the Company, which had been considered and approved by the Nomination Committee of the Board of Directors of the Company. It was agreed to appoint Mr. Xu Qian as the deputy general manager of the Company (see below for his biographical details), with the term of office being the same as that of the seventh session of the Board, effective from the date of the resolution of this meeting.