Monomer not less than 6.25 MWh! EPC Bidding for Ningxia 300MW/1200MWh Energy Storage Project!

2025-10-22 09:22:36

In the EPC bidding of Ningxia Ningdong 300 MW/1200 MWh energy storage project, the single battery compartment is ≥ 6.25 MWh, and the bidder is required to have the system integration capability and the performance of more than 1GWh.

On October 17, Ningxia Ningdong Lvke New Energy Co., Ltd. invited EPC bidding for the first phase of energy storage in the Green Power Park of Modern Coal Chemical Industry. The tenderer of the project is Ningxia Ningdong Lvke New Energy Co., Ltd.

The project is located in Ningdong Energy and Chemical Industry Base. The construction of energy storage power station is 300 MW/1200 MWh , and the capacity of each battery compartment is required to be no less than 6.25 MWh. In addition, the procurement of primary and secondary equipment for the bay shall be completed according to the access requirements of Green Pine 330 kV booster station. For EPC

project, whether mentioned in the Bidding Document or not, all work contents involving the preliminary service, survey and design, construction design, equipment procurement, project construction and installation, completion and production, file acceptance, completion settlement, project acceptance, overall completion acceptance, etc. of the project shall be within the scope of work of the Bidder.

The project requires that the bidder must have energy storage system integration capability, PCS, BMS and EMS integration capability, and at least one of them has independent R & D and production capacity, and the cumulative supply performance of energy storage system integration in the past two years is 1GWh or more.

Planned commencement date of the project: November 20, 2025; planned completion date: April 30, 2026. The project shall be able to be connected to the grid with full capacity.

All can be viewed after purchase
Correlation

In the EPC bidding of Ningxia Ningdong 300 MW/1200 MWh energy storage project, the single battery compartment is ≥ 6.25 MWh, and the bidder is required to have the system integration capability and the performance of more than 1GWh.

2025-10-22 09:22:36

In order to further study and implement Xi Jinping's thought of ecological civilization, resolutely implement the deployment requirements of the State Council's Action Plan for Continuous Improvement of Air Quality, conscientiously implement the work arrangements of the Party Committee and the government of the autonomous region, and continuously consolidate the achievements of the year of tackling key problems in the protection and control of the ecological environment, on October 15, 2026, the State Council of the People's Republic of China decided to implement the plan. The People's Government of the Autonomous Region held a kick-off meeting on air pollution prevention and control in the winter and spring of 2026-2027. Vice Chairman Liu Jun presided over and delivered a speech. Members of the leading group of the construction of ecological civilization of the Party Committee of the Autonomous Region are responsible for comrades, members of the team of the Department of Ecological Environment and relevant departments and institutions.