According to the incomplete statistics of digital new energy DataBM. Com, from November 17 to November 23, 2025, there were 6 EPC general contracting projects for photovoltaic power plants in China , with a total installed capacity of 0.46 GW. The total amount of winning bids is 1.09 billion yuan.
Among them, the second phase of the 555 MW fishing-photovoltaic complementary project of CGN New Energy in Jianhu County, Jiangsu Province, located in Jiangsu Province, was jointly won by China Energy Construction Group Jiangsu Electric Power Design Institute Co., Ltd. for 567 million yuan, with a unit price of 2.84 yuan/W and a total installed capacity of 200 MW.