31GW! Annual Photovoltaic Module Framework of China Power Construction Company is included in the Bidding for Centralized Procurement Project

2025-12-04 17:27:32

The total installed capacity of this tender is 31 GW, including 24 GW of TOPCon modules, 3 GW of HJT modules and 4 GW of BC modules. The size requirements are double glass 182mm and above. The application scope of modules includes domestic and overseas photovoltaic power generation projects.

On December 3, the announcement of public bidding for the centralized procurement project of photovoltaic module framework of China Electric Power Construction in 2026 was issued. The total installed capacity of this

tender is 31 GW , of which, the procurement scale of TOPCon components is 24 GW, HJT components are 3 GW, BC components are 4 GW, and the size requirements are double glass 182mm and above. The application scope of the module includes domestic and overseas photovoltaic power generation projects.

This tender is divided into three packages for bidding, and potential bidders can bid for one package or all packages. In terms of

performance requirements, Package 1 requires the bidder's supply performance of N-type Topcon monocrystalline silicon photovoltaic modules in the past three years (from January 2023 to the present) to be no less than 2000MWp;

Package 2: the supply performance of N-type HJT monocrystalline silicon PV modules in recent three years (from January 2023 to the present) is not less than 500MWp;

Package 3: the supply performance of monocrystalline silicon PV modules in recent three years (from January 2023 to the present) is not less than 1,000MWp. Consortium bidding is not accepted

in this tender. The deadline for submission of

bidding documents (bidding deadline, the same below) is 10:00 on December 24, 2025.

It is worth noting that this tender will determine the shortlisted suppliers of photovoltaic modules of China Power Construction Group (Stock) Co., Ltd. in 2026 according to each package (the number of shortlisted suppliers will be determined according to the actual number of bidders), and sign a framework agreement, which will be valid until the results of centralized procurement in the next year are officially announced. The purchase of photovoltaic modules of various specifications and models by the subsidiaries of the Group (Joint Stock) Company shall be carried out in accordance with the framework shortlist and agreement.

In addition to special circumstances, the sub-enterprises of the group (joint-stock) company will directly invite the shortlisted suppliers to determine the final transaction unit of the photovoltaic modules they need through negotiation or bidding procurement, and sign the procurement contract after the project landing and the specific procurement needs are clear, according to the bidding results. No separate bidding will be conducted. In 2026, China Power Construction Group (Stock) Co., Ltd. will summarize the total procurement demand on a quarterly basis, carry out the centralized secondary competition in each quarter within the scope of the shortlisted suppliers, and determine the suppliers for the transaction.

In addition, on the same day, China Electric Power Construction also issued a public tender announcement for the centralized procurement project of photovoltaic inverter framework in 2026. The inverter required for the photovoltaic power generation project of the subsidiary enterprise in 2026 will be purchased in a centralized manner by means of public bidding. The inverter will be purchased in three packages with a scale of 31 GW. The deadline for submission of

bidding documents (bidding deadline) is also 10:00 on December 24, 2025.

All can be viewed after purchase
Correlation

The total installed capacity of this tender is 31 GW, including 24 GW of TOPCon modules, 3 GW of HJT modules and 4 GW of BC modules. The size requirements are double glass 182mm and above. The application scope of modules includes domestic and overseas photovoltaic power generation projects.

2025-12-04 17:27:32

The project plans to purchase 182 mm and above N-type TOPCon modules, with an efficiency requirement of 22.7% and above, and a purchase capacity of 3GW, including 2.4G W for double-sided modules and 0.6G W for single-sided modules.

2025-12-02 09:15:38

Over the vast Gobi, delivery vehicles, like steel dragons, meander hundreds of miles through the scorching sun and dust-this is the shocking scene of Xiexin Integration successfully completing the delivery of 1.23 GW photovoltaic modules from Shenneng Xinjiang Hefeng.

2025-09-28 17:45:55

Zhejiang Aikang plans to invest in the construction of HJT perovskite tandem battery research and production base project in Hangzhou Qianjiang Economic Development Zone in the future, with a total investment of about 1 billion yuan.

2023-12-30 23:07:59

The project will invest in the construction of 3GW perovskite photovoltaic modules and 1200 tons of perovskite materials per year, and simultaneously plan project of 30GW perovskite modules, the project of 10000 tons of perovskite materials per year and the project of perovskite module equipment. At the same time, the project will rely on Fuyang Institute of Advanced Studies to set up a perovskite battery research Institute.

2023-12-30 23:04:35

The first large-scale distributed photovoltaic project in Songyuan City, Jilin Province

2023-11-28 15:47:06

TBEA Zhundong 200,000 tons of high-end electronic grade polysilicon green low-carbon circular economy phase I 100,000 tons project has been completed, and is currently in the process of reaching quality and production.

2023-11-16 17:07:55

Hongjun New Heterojunction Solar Cell and Module Production Base held the preliminary delivery of the plant and the entry ceremony of the production equipment.

2023-11-16 11:23:47

The base is planned to have two fully automated production lines, with an annual production capacity of 1.8GW and an output value of 3 billion yuan.

2023-11-10 10:35:12

Will supply Mattel Battery Factory.

2023-11-10 09:19:35

On March 10 this year, Zhengqi Holdings and Ma'anshan Municipal Government signed a contract for the industrialization project of intelligent manufacturing of 20g W high-efficiency N-type batteries.

2023-11-07 09:52:30

The total investment of Guosheng Heterojunction 10g W Double Carbon Industrial Park Project is planned to be 5.2 billion yuan.

2023-11-07 09:30:52

The total investment of the project is more than 6.8 billion yuan, and 30 N-type high-efficiency battery production lines have been built.

2023-11-06 09:25:30

Mubang Hi-Tech, Yidao New Energy and Xinzhou Economic Development Zone Management Committee jointly signed an investment agreement for the project of pulling 20GW N-type monocrystalline silicon rods annually.

2023-11-02 10:07:29

Liansheng Science and Technology Nantong 12 GW Heterojunction Battery Project will start construction this year, with a total investment of 7 billion yuan, and the project will be divided into three phases.

2023-10-30 10:15:30

On October 27, less than a month after the first phase of monocrystalline silicon project in Sany Shuozhou was put into operation, Sany Group successfully cooperated with Pinglu District, Shuozhou City, Shanxi Province, to increase the integrated layout of the whole photovoltaic industry chain.

2023-10-30 10:12:49

Successfully signed the cooperation agreement between Sanyi Shuozhou Phase II Large-size Ultra-thin Monocrystalline Silicon Wafer Project and Sanyi Group Pinglu District Distributed Photovoltaic Power Generation Project.

2023-10-27 17:21:07

The company's secretary said that the first GW production line of the company's photovoltaic cell project has been successfully trial-produced and has the conditions for production.

2023-10-26 09:55:48

The project will be listed for sale in the near future and will start construction within next year.

2023-10-24 10:22:58

On the evening of October 22, Yisheng Science and Technology announced that it planned to invest in the construction of "New Energy 12 GW Heterojunction Battery Project" with an investment of 2 billion yuan in the first phase.

2023-10-23 10:59:56

At 11:58 on September 18, the first TOPCon high-efficiency battery of Bangjie New Energy Yangzhou Base Phase I was successfully launched, which means that Bangjie has taken an important step in transforming the new energy industry.

2023-09-25 15:03:00

As a major project, Zhongqing Advanced Battery Manufacturing (Chizhou) Co., Ltd. participated in the signing of a centralized contract at the opening ceremony with an annual output of 12 GW high-efficiency TOPCON photovoltaic cell project (with an investment of 1.2 billion yuan in the first phase).

2023-09-21 11:47:47

The project was formally signed and settled on February 23 this year, and construction began on March 15. From the signing of the contract to the construction and then to the full production, the project has achieved 150 days of first-line production and 180 days of full production.

2023-09-21 11:41:38

Liansu Group will continue to expand 1.2G W PV module production line in Indonesia, featuring new energy materials, new energy equipment and new energy applications, to form an international PV module production center with a scale of about 2.4G W.

2023-09-20 11:04:22

After the completion of the second phase of the project, it will have the production capacity of 10g W crystalline silicon solar slices and 10g W batteries every year.

2023-09-20 10:52:19

On September 4, the first monocrystalline furnace of Shuangliang Phase III 50GW monocrystalline silicon project was successfully installed, marking that the main production equipment of Phase III project formally entered the installation stage, laying a solid foundation for the early commissioning of Phase III project.

2023-09-11 11:12:03

The highest power module in the mass production heterojunction module reaches 720 W.

2023-09-06 13:12:16

From November 24, 2025 to November 30, 2025, Hubei Province has the highest opening rate of cement kilns in all provinces in China, with the opening rate of 67.34%. Kiln opening rate of 50% and above: 63.13% in Jiangsu Province, 61.65% in Shaanxi Province, 60.56% in Anhui Province and 53.57% in Hainan Province.