On December 4, the Administrative Office of Altay Prefecture in Xinjiang issued a public announcement on the completion of the 23rd rectification task of the first round of feedback from the supervision of ecological environment protection in the autonomous region, which lasted for 10 working days from December 4 to December 17, 2025.

1. Rectification task:
The implementation of the peak-shifting production policy in the cement industry is not in place. According to the requirements of the Notice on Issuing the Cement Peak-Staggered Production Plan from 2023 to 2024 (Xin Gong Xin Building Materials [2023] No.4) jointly issued by the Autonomous Region, the Corps and the Ecological Environment Department, the shutdown time of cement enterprises in Altay is from November 1 to April 15 of the next year and from June 1 to 30. Habahe Ashan Cement Co., Ltd. failed to implement the peak-staggering production plan, failed to shut down the kiln within the specified time period as required, and was still in production, with a cumulative production of 119,000 tons of clinker .
2. Rectification time limit
before
December 31, 2025 3. Rectification target
Habahe Ashan Cement Co., Ltd. implements the main responsibility of the enterprise and implements the peak staggering production work in strict accordance with the requirements of the autonomous region.
4. Rectification measures
First, in accordance with the principle of "government supervision and guidance, association organization and implementation, and enterprise initiative implementation", implement the "Annual Cement Peak-Staggered Production Plan" to carry out peak-staggered production, which can be adjusted after approval by the autonomous region. To carry out guidance and inspection during peak staggering production of Ashan Cement Co., Ltd. in Habahe County.
Secondly, in view of the problem that Ashan Cement Co., Ltd. failed to implement the policy requirements of peak-staggering production in accordance with the Notice on Issuing Peak-staggering Production of Cement from 2023 to 2024, the enterprise legal person was interviewed.
Third, Ashan Cement Co., Ltd. of Habahe County has implemented the Cement Peak-Staggered Production Plan from 2024 to 2025.
5. Completion
(1) Completion of
rectification objectives On October 29, 2025, Habahe County carried out self-inspection work. On November 4, 2025, the Regional Bureau of Industry and Information Technology and the Bureau of Ecological Environment formed an acceptance expert group, led by Comrade Dawule, a member of the Party Group and deputy director of the Regional Bureau of Industry and Information Technology, to conduct regional acceptance in Habahe County. The acceptance team believes that Ashan Cement Co., Ltd. of Habahe County has implemented the peak-staggering production policy of the cement industry in the autonomous region as required in 2025, implemented various rectification requirements, standardized and complete archives, completed the rectification task, and met the marketing conditions.
(2) The implementation of
浙公网安备33010802003254号