Recently, the Forestry Bureau of Guichi District issued the Announcement on the Completion of the Rectification of the Photovoltaic Problem in the Construction of Shengjin Lake National Nature Reserve by Chizhou Conch Cement Co., Ltd. of Anhui Province, which was found in the verification of the "Green Shield" Nature Reserve in 2024. According to
the announcement, Anhui Chizhou Conch Cement Co., Ltd. has occupied the No.2 photovoltaic point of Shengjin Lake National Nature Reserve. The rectification measures require that the photovoltaic facilities in the protected area be demolished and the waste after demolition be properly handled, and that a long-term management mechanism be established and improved to prevent similar problems from happening again.
At present, Chizhou Conch has completed the rectification according to the above requirements. The inspection of "Green Shield" Nature Reserve in
2024 found that the problem of Anhui Chizhou Conch Cement Co., Ltd. encroaching on the No.2 photovoltaic point (202403-341702-N1-041-ED-0002) of Shengjin Lake National Nature Reserve has been rectified and passed the self-inspection and acceptance. According to the requirements of the Notice of the Office of the Chizhou construction of ecological civilization and Eco-environmental Protection Committee on the Rectification and Marketing of the "Green Shield" Nature Reserve, The completion of the rectification of the problem is announced as follows:
I. Rectification problem
Anhui Chizhou Conch Cement Co., Ltd. encroaches on the construction of No.2 photovoltaic point in Shengjin Lake National Nature Reserve (202403-341702-N1-041-ED-0002).
2. Niutoushan People's Government
, the main body
of rectification and implementation, 3. Key measures
1. To urge the company to dismantle the photovoltaic facilities in the protected area and properly dispose of the dismantled waste.
2. Establish and improve a long-term management mechanism to prevent similar problems from happening again.
4. The target task is
to dismantle the photovoltaic facilities in the protected area and restore the original appearance.
5. The completion time limit
is the end of
June 2025. 6. The completion of
rectification 1. The company has dismantled the photovoltaic facilities in the protected area and properly disposed of the dismantled waste.
2. The company has established and improved a long-term management mechanism to prevent similar problems from happening again.
If there is any objection to the completion of the rectification of the above problems, please give feedback to the Forestry Bureau of Guichi District, Chizhou City during the publicity period (July 7, 2025 to July 9, 2025, a total of 3 working days).
Supervisor Tel: 0566-3397580;
E-mail: 1079440549@qq.com. Forestry Bureau
of Guichi District
, Chizhou City, July 7