On September 28, the 50 MW photovoltaic power generation project (EPC) of Hongyazi Green Power Park of Deqi Photovoltaic Technology Co., Ltd. in Pingluo County, Shizuishan City, Ningxia Hui Autonomous Region issued a change announcement.

On September 28, the announcement of 50 MW change" in Hongyazi Green Power Park of Deqi Photovoltaic Technology Co., Ltd. in Pingluo County, Shizuishan City, Ningxia Hui Autonomous Region showed that. The actual installed capacity of the project is changed from 59.4425MWp to 59. The specific changes are as follows:

SRC = "The total duration of the https://img7.ccement.com/news/2509/richtext/img/wvtbpldelt1759135697858. project is 90 days .".

On the same day, the EPC project of 5990KW distributed photovoltaic power generation project (Phase I) of Dawan Electric Power Development Co., Ltd. in Congjiang County, Qiandongnan Miao and Dong Autonomous Prefecture, Guizhou Province, issued a change announcement.

The announcement shows that the tenderer of the project has been changed from Congjiang County Dawan Electric Power Development Co., Ltd. to Beizheng (Yunnan) Agriculture and Animal Husbandry Science and Technology Co., Ltd . At the same time, the bid opening time is also postponed from 14: 00 on September 29, 2025 to 9:00 on October 13, 2025. Other changes are as follows:

in which the erection area of the steel structure is 26000 square meters, The "full connection" mode.

In terms of construction period, the total construction period of the project is 180 calendar days .

All can be viewed after purchase
Correlation

On September 28, the 50 MW photovoltaic power generation project (EPC) of Hongyazi Green Power Park of Deqi Photovoltaic Technology Co., Ltd. in Pingluo County, Shizuishan City, Ningxia Hui Autonomous Region issued a change announcement.

2025-09-29 16:49:34

The Port Coal Price Statistics Table shows the price changes of different coal types in the ports around Bohai Sea, East China, Jiangnei and South China on September 18 and September 25, 2025. There is no change in the price of some coal types in some ports. In the case of price change, the price change of some coal types in some ports is relatively large, reaching a certain value, while the price change of general bituminous coal with 5500 calorific value and 5000 calorific value in Jingjiang Yingli Port is relatively small, only 5.