on September 9, the rotary kiln of Line A of Nigeria ITORI 2 × 6000t/d clinker cement production line project contracted by Sinoma International (Nanjing) and constructed by Suzhou Sinoma was successfully closed. The rotary kiln of the
project is designed to have 9 sections with a total length of 74 meters. In the construction preparation stage, the project management personnel and the subcontractor, after careful discussion, formulated a detailed and comprehensive hoisting plan, carried out detailed safety technical disclosure to all employees, emphasized safety measures and operation specifications, and made every effort to ensure the safety of personnel and equipment in the hoisting process. Finally, the project department overcame many difficulties such as high temperature, rainy weather and mosquito infestation, and completed the hoisting of rotary kiln on time and with high quality, which was highly praised by the owner's management team. The successful closure of the
rotary kiln marks that the ITORI project has achieved phased construction results, which greatly inspires the confidence of all project personnel in the high-quality performance of the project. The project department will continue to uphold the "iron army spirit", adhere to the construction concept of "safety first, quality first", strive for excellence, and go all out to build this project into a high-quality benchmark project in West Africa.