Abolish the bid and make a new move! Second Bidding for Two Photovoltaic Projects in Yunnan

2025-09-17 17:18:07

On September 16, the EPC general contracting project of distributed photovoltaic power generation project in Tonghai County, Yuxi City, Yunnan Province (the first bid section) issued the second tender announcement, and the tenderer was Zhongpeng Energy Tonghai Co., Ltd.

On September 16, the distributed " in Tonghai County, Yuxi City, Yunnan Province, was noteworthy. The project was first tendered in December 2024 by a consortium

of China Construction Third Engineering Bureau Group Co., Ltd. and Zhongji Zhonglian Engineering Co., Ltd. The project also issued a notice of abolition because the first winning bidder voluntarily gave up the qualification to win the bid. (For details, please click: " It is reported that the project is located in Tonghai County, Yuxi, Yunnan. It is planned to invest 940 million yuan in the construction of about 833. Among them, the roof distributed photovoltaic power generation project (Phase I) in Tonghai County (Industry and Commerce) totals 333.

The EPC construction scale of the distributed photovoltaic power generation project undertaken by the winning bidder has been reduced from 550 MW to 300 MW .

This tender requires that the total unit price quotation of the bidder shall not exceed 3.

In addition, the total construction period of the project is two years , and the calculation of the construction period will start from the time when the supervisor issues the commencement order. Consortium bidding is accepted for

this project . In case of consortium bidding, the following requirements shall be met:

It is noteworthy that the new village photovoltaic power generation project in Xuanwei City, Qujing City, Yunnan Province, also issued a second tender announcement on September 16 because the winning bidder abandoned the bid . The installed capacity is 40,000 kilowatts .

The project is located in the new village of Lefeng Township, Xuanwei City. Estimated total investment 1. The bidding scope is as follows:

that this tender does not accept joint bidding Body bidding. The bid

closing/opening time is 9:00 on October 11, 2025.

It is noteworthy that a number of photovoltaic projects in Yunnan have recently been abandoned after winning the bid. For example, the 90 MW photovoltaic power generation project in Baihe Village, Chuxiong Prefecture, Yunnan Province, and the 40 MW photovoltaic power generation project across the Shishan River. (For more information, please click .

All can be viewed after purchase
Correlation

On September 16, the EPC general contracting project of distributed photovoltaic power generation project in Tonghai County, Yuxi City, Yunnan Province (the first bid section) issued the second tender announcement, and the tenderer was Zhongpeng Energy Tonghai Co., Ltd.

2025-09-17 17:18:07

Czech PSP Engineering Company has signed the largest overseas cement general contracting order in Uzbekistan, and will build a new cement plant with an annual output of 1 million tons for local owners in Jizak, which will be delivered in early 2028 and will cover 5% of Ukraine's cement output after putting into operation. The project has two international "foreign aid", Turkish enterprises are responsible for the integration of process packages and key equipment, and Czech supporting enterprises undertake some modules. The funds are provided by the International Investment Fund, and the PSP collection is linked to the construction node. The project is the largest PSP project in Central Asia and the Middle East with the highest degree of technology integration, and will radiate to the surrounding market after being put into operation.