Xinjiang 1GW Photovoltaic Project Photovoltaic Area Bid Section 1 EPC General Contracting Bidding!

2025-09-29 13:19:30

On September 28, Xinjiang Tarim Oilfield Bazhou Ruoqiang 1 million kilowatt photovoltaic power generation project EPC general contracting tender for photovoltaic area 1 tender section. The owner of the project is Tarim Oilfield (Ruoqiang) New Energy Co., Ltd. and the tenderer is Tarim Oilfield Branch of PetroChina Company Limited.

On

28 September, The owner of Xinjiang Tarim Oilfield Bazhou Ruoqiang 1000MW Tarim Oilfield (Ruoqiang) New Energy Co., Ltd . The tenderer is Tarim Oilfield Branch of PetroChina Company Limited.

Tarim Oilfield Bazhou Ruoqiang 1 million kilowatt photovoltaic power generation project is located 27 kilometers south of Ruoqiang County , Bazhou, Xinjiang. The installed capacity is 1 million kilowatts on the AC side . DC side 122.

The project supports the construction of a 220 kV step-up gathering station and a 100 MW/200 MWh lithium iron phosphate battery

The scope of this tender is EPC general contracting of Bid Section 1 of Ruoqiang Photovoltaic Power Generation Project in Bazhou, Tarim Oilfield. The content of the project is the construction drawing design of the first bid section and the second bid section of the photovoltaic area. Procurement of materials supplied by Party B, engineering construction, monomer commissioning, grid-connected trial operation , etc. In the first bid section of the photovoltaic area. As follows:

In addition, the project is scheduled to start on October 30, 2025, the main project is completed on August 10, 2026 and has the conditions for grid connection, the grid connection is on September 10 of the same year, and the full capacity grid connection is on January 30, 2027. The bid

closing/opening time is 8 o'clock on October 21, 2025.

All can be viewed after purchase
Correlation

On September 28, Xinjiang Tarim Oilfield Bazhou Ruoqiang 1 million kilowatt photovoltaic power generation project EPC general contracting tender for photovoltaic area 1 tender section. The owner of the project is Tarim Oilfield (Ruoqiang) New Energy Co., Ltd. and the tenderer is Tarim Oilfield Branch of PetroChina Company Limited.

2025-09-29 13:19:30

The Port Coal Price Statistics Table shows the price changes of different coal types in the ports around Bohai Sea, East China, Jiangnei and South China on September 18 and September 25, 2025. There is no change in the price of some coal types in some ports. In the case of price change, the price change of some coal types in some ports is relatively large, reaching a certain value, while the price change of general bituminous coal with 5500 calorific value and 5000 calorific value in Jingjiang Yingli Port is relatively small, only 5.