On October 15, Jiangsu Huadian Changzhou Wujin Qianhuanglingtai 219 MW Fishing-photovoltaic Complementary Photovoltaic Project EPC general contracting successful candidates were announced. The consortium formed by China
Huadian Science and Engineering Group Co., Ltd. and Jiangsu Electric Power Design Institute Co., Ltd. of China Energy Engineering Group is the first successful candidate with a 61259 of RMB 0.28 million, and its average unit price is RMB 2.798/W (calculated on the AC side).
It is reported that the tenderer of the project is Huadian Jiangsu Changzhou New Energy Co., Ltd. The installed capacity is 260.3272 MW (218.96 MW on AC side). The construction period of the project is 8.5 months, and it is planned to start in October 2026.