Recently, the 200MW/800MWh independent new energy storage EPC project in Wusu City, Xinjiang issued a tender termination announcement. The original bid opening time of the project was October 21. The reason for the termination was that the project had undergone major changes.
The project is an independent new energy storage project, with an EPC bidding budget of 823 million yuan. According to the original construction period, the project needs to complete grid-connected commissioning before September 30, 2027, and achieve commercial operation before December 30, 2027.
It is reported that the project has been terminated after a tender, and in January 2026, the announcement of successful candidates was issued. The first successful candidate is Jiangxi Electric Power Construction Co., Ltd. of China Electric Power Construction Group, with a bid price of about 750 million yuan.
However, in June 2026, the project announced that it would restart bidding because the winning bidder could not perform.