On July 1, the tender for the EPC general contracting procurement project of the second bid section of the 500MW photovoltaic composite project in Lingwu City was issued, and the tenderer was Lingwu Linglu New Energy Co., Ltd. The
project is located in Majiatan Town, Lingwu City, Ningxia, with a total investment of 1.25 billion yuan, a construction scale of 500 MW photovoltaic, supporting 100 MW/400 MWh energy storage facilities . Bidders are required to have the completion performance of two or more similar photovoltaic projects with a single capacity of not less than 100MW since 2023, and consortium bidding is not accepted. It is planned to start construction on August 10, 2026 and connect to the grid with full capacity on December 30. The deadline for bidding and bid opening is 9:00 on July 23, 2026.
The project had previously completed the EIA acceptance announcement in June, and the EPC tender for the first bid section was launched on June 8.