Jilin Yatai Cement's 9000t/d clinker production line is planned to be put into operation one year later

2026-03-18 09:49:12

The original planned ignition production time is changed from December 2027 to December 2028; the replacement capacity withdrawal time is changed from December 2027 to December 2028.

On March 13, Jilin Provincial Office of Industry and Information Technology announced the change of capacity replacement plan for the construction project of Jilin Yatai Cement Co., Ltd. with a daily output of 9000 tons of cement clinker .

Combined with the new and old replacement scheme, the original construction subject is changed from Jilin Yatai Building Material Environmental Protection Technology Co., Ltd. to Jilin Yatai Cement Co., Ltd.;

the original planned ignition and production time is changed from December 2027 to December 2028; The withdrawal time of

replacement capacity is changed from December 2027 to December 2028.

All can be viewed after purchase
Correlation

The original planned ignition production time is changed from December 2027 to December 2028; the replacement capacity withdrawal time is changed from December 2027 to December 2028.

2026-03-18 09:49:12

Overall, the price of cement in Kunming has been running to the bottom of the stage, and the downward space is limited. The key to the follow-up trend lies in two points: one is whether the regional demand can show signs of improvement in the seasonal peak season window, providing room for the price increase to be digested; the other is whether the major local manufacturers can maintain a unified price increase implementation discipline, so as to avoid the price increase being aborted due to some enterprises soliciting goods at low prices.