Jilin Yatai Cement's 9000t/d clinker production line is planned to be put into operation one year later

2026-03-18 09:49:12

The original planned ignition production time is changed from December 2027 to December 2028; the replacement capacity withdrawal time is changed from December 2027 to December 2028.

On March 13, Jilin Provincial Office of Industry and Information Technology announced the change of capacity replacement plan for the construction project of Jilin Yatai Cement Co., Ltd. with a daily output of 9000 tons of cement clinker .

Combined with the new and old replacement scheme, the original construction subject is changed from Jilin Yatai Building Material Environmental Protection Technology Co., Ltd. to Jilin Yatai Cement Co., Ltd.;

the original planned ignition and production time is changed from December 2027 to December 2028; The withdrawal time of

replacement capacity is changed from December 2027 to December 2028.

All can be viewed after purchase
Correlation

The original planned ignition production time is changed from December 2027 to December 2028; the replacement capacity withdrawal time is changed from December 2027 to December 2028.

2026-03-18 09:49:12

Through the closed-loop management of the whole process, cement enterprises can meet the requirements of double control of carbon emissions, reduce the cost of performance, tap the value of carbon assets, adapt to the new stage requirements of double carbon strategy from system construction to full implementation, and realize the coordinated promotion of low-carbon transformation and high-quality development.