On March 17, Shaanxi Provincial Office of Industry and Information Technology issued the "Announcement on the Replacement Scheme of Supplementary Capacity for Jidong Heidelberg (Fufeng) Cement Co., Ltd. and Jidong Heidelberg (Jingyang) Cement Co., Ltd." And the "Announcement on the Replacement Scheme of Supplementary Capacity for Tongchuan Shengwei Building Materials Co., Ltd. and Shaanxi Shengwei Building Materials Group Co., Ltd.".

Jidong Heidelberg (Fufeng) Cement Co., Ltd. withdrew from a 3000t/d clinker production line , of which 1500t/d capacity was used to supplement a 4500t/d clinker production line in the same plant area, and the capacity was 6000t/d after the supplement. The replacement ratio is 1:1; in addition, a 4500t/d clinker line of Jidong Heidelberg (Jingyang) Company is supplemented with a capacity of 1500t/d, and the capacity is 5250t/d after supplementation, and the replacement ratio is 2:1.


Tongchuan Shengwei Building Materials Co., Ltd. withdraws from a 5000t/d clinker production line , of which the capacity of 2100t/d is used to supplement another 4500t/d clinker production line in the same plant area. After completion, the capacity is 6600t/d, and the replacement ratio is 1:1; In addition, the production capacity of 2900t/d is used to supplement a 4500t/d clinker line of Shaanxi Shengwei Building Materials Group, with a production capacity of 5950t/d and a replacement ratio of 2:1.


浙公网安备33010802003254号