On March 16, the Office of Industry and Information Technology of Hebei Province announced that it would cancel the announcement of the capacity relocation plan of the 4500t/d new dry clinker production line construction project of Yanxin Holding Group Co., Ltd. on November 20, 2023.
According to the previous announcement of Hebei Industry and Information Technology Department, Yanxin Holdings originally planned to use a 2500t/d and a 2000t/d clinker production line in the plant to relocate a 4500t/d new dry clinker production line with a replacement ratio of 1:1.
According to the statistics of cement network APP, a total of four clinker production lines will not be constructed in 2026, with a total capacity of 6.82 million tons (calculated according to 310 days). The details are as follows:

According to the big data of cement, there are still about 30 clinker production lines in the preparation stage in the current system. Considering the development pressure faced by the industry, more production lines will not be constructed or will be postponed in the future.

浙公网安备33010802003254号