The amount involved was 905 million yuan! Sinoma International won the first trial against Guangxi Jinxiang Cement

2026-04-02 09:28:13

Up to now, Sinoma International has made a cumulative provision for impairment of the receivables involved in the lawsuit of RMB46,000,900. As the case is still in the appeal period and the final result is uncertain, it is impossible to accurately judge the impact on the company's profits in 2026 and beyond.

On the evening of April

1, Sinoma International issued a major litigation progress announcement, and the case of the company suing Guangxi Jinxiang Cement Co., Ltd. for construction contract disputes has been adjudicated in the first instance. The amount of money involved in the case was about 905 million yuan, and the court ordered Guangxi Jinxiang to pay Sinoma International more than 776 million yuan of project funds and corresponding interest, deferred payment interest of more than 47.23 million yuan. Sinoma International enjoyed the priority of compensation for the discount or auction price of the project involved in the case within the scope of arrears of project funds, and other litigation requests of the company were rejected.

Up to now, Sinoma International has made a cumulative provision for impairment of the receivables involved in the lawsuit of RMB46,000,900. As the case is still in the appeal period and the final result is uncertain, it is impossible to accurately judge the impact on the company's profits in 2026 and beyond. According to the data map

of

Guangxi Jinxiang Cement, on November 1, 2025, Sinoma International announced that it had filed a lawsuit with Laibin Intermediate People's Court for a construction contract dispute with Guangxi Jinxiang Cement. In 2021, the two sides signed the EPC General Contract for 2 × 6000t/d Clinker Cement Production Line and 6 million tons of Aggregate Production Line of Guangxi Jinxiang Cement Co., Ltd. and confirmed the project settlement price of 1.9595 billion yuan in 2024. Sinoma International has performed the contract, but Guangxi Jinxiang still owes the principal and interest of the project payment. The company appeals to the other party to pay the principal and interest of the arrears totaling about 905 million yuan, and enjoys the priority of compensation for the project involved in the case, and the other party shall bear the litigation related costs. (Link: Recovery of 905 million yuan of project funds! Sinoma International Sues Guangxi Jinxiang Cement!

All can be viewed after purchase
Correlation

Up to now, Sinoma International has made a cumulative provision for impairment of the receivables involved in the lawsuit of RMB46,000,900. As the case is still in the appeal period and the final result is uncertain, it is impossible to accurately judge the impact on the company's profits in 2026 and beyond.

2026-04-02 09:28:13

The planned land area of this project is about 35272. 27 square meters, the net land area is about 26207 square meters, and the total construction area is about 238544. 45 square meters. Among them, the capacity building area is 172336. 65 square meters, including the 129540 of resettlement housing, the 10423 of public service facilities and municipal service facilities, the 31573 of resettlement property and other capacity area of 800 square meters; The floor area excluding capacity is 66207.8 square meters (the 58607 of the basement is.8 square meters). The building is 100 meters high, with three floors underground and five buildings with 32 floors above ground.