Guizhou 178MW Photovoltaic Power Station Project is planned to invite tenders!

2026-04-29 17:28:50

On April 29, the public service platform for bidding in Guizhou Province released the bidding plan for the photovoltaic power station project in Lanhua Village, Yingpan Township, Shuicheng District, and the photovoltaic power station project in Yingpan Village, Shunchang Township, Shuicheng District. The tenderer is Guizhou Energy Shuicheng Coal and Electricity Integration Co., Ltd.

On April 29, the bidding public service platform of Guizhou Province issued the bidding plan for the Lanhua Village Photovoltaic Power Station Project in Yingpan Township, Shuicheng District, and the Yingpan Village Photovoltaic Power Station Project in Shunchang Township, Shuicheng District. The tenderer is Guizhou Energy Shuicheng Coal, Electricity and Chemical Integration Co., Ltd .

Among them , the total investment of the photovoltaic power station project in Lanhua Village, Yingpan Township, Shuicheng District is 37243 95000 yuan , located in Shuicheng District, Liupanshui City, Guizhou Province. The planned capacity of

the project is 78 MW , and the actual installed capacity is 110.0736 MWp (DC side). The photovoltaic field area is connected to the 110 kV Lanhua booster station by three 35 kV collector lines. The 110kV Lanhua booster station is connected to the 110kV Faer power station by a 110kV line, with a line length of about 5km and a conductor section of 1 × 185 mm ². Located in Shuicheng District, Liupanshui City, Guizhou Province, the photovoltaic power station project in Yingpan Village, Shunchang Township

贵州178MW光伏电站项目计划招标!1

, Shuicheng District, with a total investment of 47187 5800 yuan . The

planned capacity of the project is 100MW , and the actual installed capacity is 140.MWp 97888 (DC side). The photovoltaic field area is connected to the 110kV Yingpan booster station by four 35kV collector lines. The 110kV Yingpan booster station will build a new 110kV line connected to the 110kV Miluo substation. The new line is about 9.5km long, and the conductor section is 1 × 240mm ².

贵州178MW光伏电站项目计划招标!2

All can be viewed after purchase
Correlation

On April 29, the public service platform for bidding in Guizhou Province released the bidding plan for the photovoltaic power station project in Lanhua Village, Yingpan Township, Shuicheng District, and the photovoltaic power station project in Yingpan Village, Shunchang Township, Shuicheng District. The tenderer is Guizhou Energy Shuicheng Coal and Electricity Integration Co., Ltd.

2026-04-29 17:28:50

On May 6, 2026, Huang Linmu, Party Secretary and Chairman of Guoyuan Financial Holding Group, and Wei Lixiang, Deputy Party Secretary and General Manager, visited Conch Group. Conch Group Party Secretary and Chairman Yang Jun, Deputy Party Secretary and General Manager Zhu Shengli, and Deputy General Manager Ding Feng warmly received Huang Linmu and his delegation.