Recently, several subsidiaries of China Construction Group Co., Ltd. (Hereinafter referred to as "China Construction Group") have successively won major projects in the fields of industry, energy, municipal and educational infrastructure, with a total bid amount of about 6.8 billion yuan. Design-procurement-construction general contracting of
Chongqing Tianxinyuan Copper Co., Ltd. 200,000t/a Scrap Copper Recycling and Comprehensive Utilization Project (Phase I).
The project is located in Zone B of Beidu Aluminum Industrial Park, Qijiang Industrial Park, Qijiang District, Chongqing. It is planned to build a pyrometallurgical workshop and an electrolytic workshop, supporting public, auxiliary, storage and transportation and environmental protection facilities, including a reduction smelting furnace, two anode furnaces, two double-disc casting machines and electrolysis and purification processes, with an annual output of 200000 tons of A-level cathode copper. The total investment is about 1.2 billion yuan.
Bid winner: China Construction Eighth Engineering Bureau No.2 Construction Co., Ltd. (United Mining and Metallurgy Technology Group, Chongqing Daheng Engineering Design), bid price: 1.189725 billion yuan.
High-end Electronic Measuring Instrument Innovation and Industrial Conditions Construction Project (Construction), located at No.98 Xiangjiang Road, Huangdao District, Qingdao City.
The total building area is 86,380.2 square meters, including about 32,000 square meters of technology innovation center and about 54,000 square meters of production line transformation and expansion. It is a 20-storey building above ground and 3-storey building underground, with a height of about 99 meters.
Bid winner: China Construction Eighth Engineering Division First Construction Co., Ltd., bid price: 466.8 million yuan. Located in Futian District, Shenzhen City, this project is the general contractor of the reconstruction project of the old residential area (shanty town) of Xiangmi Second Village
, Lianhua Street. The 27726 of the land for development and construction is 0.6 square meters, the planned plot ratio is 5.5, the total construction area is about 240,000 square meters, and the estimated value of the contracted project is 1.0201 billion yuan.
Bid winner: China Construction Third Engineering Bureau First Construction Engineering Co., Ltd. The first phase project (1 # dock and 2 # dock) of the large ship and marine engineering equipment repair and refitting project
of Dongdadong Marine Industrial Science and Technology Park is located in Bojia Island, Renhe Town, Rongcheng City, Shandong Province.
Two new 300,000-tonnage docks (530m × 112m and 530m × 142m) will be built, including temporary cofferdam, dock area terrace, general assembly platform, crane track beam, energy center, water pump house, jetty, revetment and other supporting facilities, with an estimated contract price of 618.35 million yuan.
First place: China Construction Port Group, bid price: 594.25 million yuan.
Suining Chuanshan 200 MW Compressed Air Energy Storage and Comprehensive Energy Utilization Project is located in Chuanshan District, Suining City, Sichuan Province. The 200MW/1600 MWh compressed air energy storage power station will be
constructed, including the main plant, cold and hot water tank, heat exchange area, underground gas storage system and complex building, with a total construction period of 16 months, and will be completed on December 31, 2027.
Bid winner: China Construction Eighth Engineering Bureau Energy Construction Co., Ltd., bid price: RMB 1.0985 billion. Located in Lingang, Shanghai, the 3 # and 4 # comprehensive teaching and experimental buildings of the new campus of
East China Normal University have a total construction area of 67158 square meters, including two comprehensive teaching and experimental buildings (each 33579 square meters), with an underground 22200 of square meters and a building height of 27.7 meters.
First place: China Construction Eighth Engineering Bureau (jointly with Tongji University Design Institute), bid price: 512.77 million yuan. Plot 1002-631 (D1) and Plot 1002-632 (D3) of Electronic City West Zone, Zhongguancun Science and Technology Park, Chaoyang District,
Beijing F3 Other Multifunctional Land Use Project (D1-01 and other 24 items) Bid Section I is located in Laiguangying Township, Chaoyang District.
The total construction area is about 202,100 square meters, including 138,300 square meters above ground and 63,800 square meters underground, with an estimated contract price of 870.74 million yuan.
Bid winner: China Construction First Engineering Group Construction Development Co., Ltd., bid price: 857.21 million yuan. The 250MW/500MWh grid-side energy storage project
of Heshan Herui Energy Storage Technology Co., Ltd. is located in Zhuxi International Logistics Center, Heshan City, Jiangmen City, Guangdong Province, covering an area of 31635 square meters. It is planned to build a grid-side energy storage power station for frequency modulation and peak shaving of the grid, with 160 calendar days and full capacity connected to the grid in February 2027. The maximum price is 690 million yuan.
Bid winner: China Construction Third Engineering Bureau Group (together with Guangdong Xinneng Technology), bid price: 659 million yuan. Located in Lucheng District, Changzhi City, Shanxi Province,
the 100MW/101.75 MWh independent frequency modulation power station will be built, with 50 MW flywheel + 50 MW lithium hybrid energy storage, a new 220kV booster station and a 1.5km outgoing line. The construction period is 263 days.
First place: China Construction Second Engineering Bureau (jointly with Hubei Jianke International), bid price: 503.7 million yuan.