of Biandukou-Menyuan Section of
National Expressway G0611 Zhangye-Wenchuan Highway in Qinghai Province Construction Location: Menyuan County, Qilian County, Minle County and Shandan County in Qinghai Province
Bidding Scope: Project Starting Point K0 + 000 The terminal point is K32 + 960, with an average altitude of 3,200m, and the main control points along the line are/; the total length of the main line is 33.127 km (including two long chains of 167.083 m in total) (the length of the branch line is/km), which is constructed according to the standard of expressways with a design speed of 80 km/H, a subgrade width of 26 m, a pavement width of/m, and the design load of bridges and culverts is Class I highway. The public bidding for the pavement, traffic safety, prefabrication, tunnel, greening, electromechanical and housing construction of K0 + 000 ~ K32 + 960 (stake number range) of the project is now carried out.
Bidding scope: construction drawing design of pavement, traffic safety, prefabrication, tunnel, greening, electromechanical, housing construction and all engineering contents included in the bill of quantities within the scope of the bid section. Bid section division and planned construction period of the
bidding project: The bidding project is divided into one bid section. The division and construction period requirements of each bid section are as follows:
Bid section name: BM-SG12 of K0 + 000 ~ K32 + 960 Section of Qinghai Biandukou-Menyuan Section of National Expressway G0611 Zhangye-Wenchuan Highway.
Stake No.: K0 + 000 ~ K32 +
960 Length (km): 33.127
Main works or quantity: Pavement works of K0 + 000 ~ K32 + 960 Section, Civil engineering SG1 bid, civil engineering SG2, civil engineering SG3 bid, civil engineering SG4 bid small prefabricated components, civil engineering SG3 bid, civil engineering SG4 bid bridge prefabricated beam slab, Ebao Daling Tunnel 5 (K25 + 500 ~ K27 + 905 section) is 2.405 km long (right line YK25 + 410 ~ YK27 + 940, 2.53 km long). Traffic safety works of K0 + 000 ~ K32 + 960 section, electromechanical works of road and tunnel of K0 + 000 ~ K32 + 960 section, greening works, housing construction works (auxiliary rooms and outdoor works of Yangxiongzi parking area; water pump room and power distribution room and outdoor works of Muchangshan tunnel substation; Ebo No.3 Tunnel Substation Pump House and Power Distribution House, Outdoor Works, etc.) and other construction drawing design and all engineering contents included in the bill of quantities.
Estimated construction period: 1,340 days
Defect liability period (month): 24
Identity type required for bidding: construction unit;
Bid winning information:
Bid winner: Xinjiang Beixin Road & Bridge Group Co., Ltd. (Leader)
Qinghai No.6 Road & Bridge Construction Co., Ltd.
Qinghai Xingli Highway & Bridge Engineering Co., Ltd.
Electrification Project of CCCC First Highway Engineering Co., Ltd. Tender offer of limited company
(ten thousand yuan): 113337. 24