PowerChina Wins Bid for Two New Pumped Storage Power Station Projects

2026-05-08 10:10:15

Hebei Qianxi Pumped Storage Power Station is located in Luanyang Town and Shangying Town, Qianxi County, Tangshan City, Hebei Province, about 116 km away from Tangshan City and 177 km away from Beijing. The installed capacity of the power station is 1000 MW. The key project of the power station is mainly composed of the upper reservoir, the lower reservoir, the water conveyance system, the underground powerhouse and the switch station, the open channel of the river, the make-up pump station and other buildings. The upper reservoir is located at the head of the natural gully, and the terrain is relatively open. The reservoir basin is formed by excavation in the reservoir and damming of the main gully. The lower reservoir is located in the Changhe River valley. Due to the large sediment content of the river flow, in order to avoid the impact of the sediment flow on the unit, the upper reservoir is located in the Jinlongkou Village to Chaoyu Gully of the Changhe River.

Project name: Hebei Qianxi Pumped Storage Power Station Lower Reservoir Project (QX/C3)

Project overview: Hebei Qianxi Pumped Storage Power Station is located in Luanyang Town and Shangying Town, Qianxi County, Tangshan City, Hebei Province, about 116 km away from Tangshan City and about 177 km away from Beijing. The installed capacity of the power station is 1000 MW. The key project of the power station is mainly composed of the upper reservoir, the lower reservoir, the water conveyance system, the underground powerhouse and the switch station, the open channel of the river, the make-up pump station and other buildings. The upper reservoir is located at the head of the natural gully, and the terrain is relatively open. The reservoir basin is formed by excavation in the reservoir and damming in the main gully. The lower reservoir is located in the Changhe River valley. Due to the large sediment content of the river flow, in order to avoid the impact of the sediment flow on the unit, the downstream dam and the upstream sediment dam are built at the turning point of the Jinlongkou Village to Chaoyu Gully downstream of the Changhe River to form a special reservoir. The open channel of the river course is set up by cutting off the bend and straightening, and the flood and sediment of the long river do not enter the reservoir.

Construction site: Qianxi County, Tangshan City, Hebei Province.

Bidding scope: Hebei Qianxi Pumped Storage Power Station Lower Reservoir Project (QX/C3), including but not limited to lower reservoir civil works, lower reservoir inlet/outlet, water replenishment works, mechanical and electrical equipment installation, metal structure equipment installation, ground buildings and decoration works, Y9 water replenishment project road (permanent road), Initial impoundment and construction auxiliary facilities.

Bid winning information:

First place: Sinohydro Bureau 4 Co., Ltd.

Bid price: 31677: RMB0.777777

Second place: Sinohydro Bureau 3 Co., Ltd.

Bid price: RMB299 171,688 yuan

Third place: China Gezhouba Group No.2 Engineering Co., Ltd.

Bidding price: 32018: 1,514,760 yuan


Project name: Hebei Lingshou Pumped Storage Power Station Mechanical and Electrical Installation

Project Overview: Hebei Lingshou The pumped storage power station is located in Chenzhuang Town, Lingshou County, Shijiazhuang City, Hebei Province, about 56 kilometers away from Lingshou County, 99 kilometers away from Shijiazhuang City and 283 kilometers away from Beijing. The planned installed capacity of the power station is 1400 MW, and four pumped storage units with a single unit capacity of 350 MW are installed, which is an important green energy project serving the coordinated development of Beijing, Tianjin and Hebei.

The power station is a large (1) type first-class project, the main permanent buildings are designed as Class 1 buildings, and the secondary permanent buildings are designed as Class 3 buildings. The project is composed of upper and lower reservoir water retaining structures, water conveyance system, underground powerhouse and its ancillary buildings, water replenishment system, etc. It is a huge "green charging treasure" hidden deep in the mountain. The construction scope of the mechanical and electrical installation project in this

tender covers the installation of pump turbine and generator motor, computer monitoring system, electrical primary/secondary equipment, bridge crane, heating ventilation and air conditioning dehumidification system, fire fighting system, plant contact power cable and control protection communication optical cable and other mechanical and electrical equipment. As well as the procurement of auxiliary system pipelines and support and hanger equipment of the whole plant. In addition, the bidding scope also includes the civil engineering and interior decoration works of underground powerhouse, main transformer tunnel, outgoing line tunnel, tail gate tunnel and other parts. Concrete works, masonry works, embedded parts and pipe works of buildings such as

underground powerhouse installation room, main engine room, auxiliary powerhouse, main transformer tunnel, main transformer auxiliary powerhouse, outgoing line adit, outgoing line adit, medium and low voltage cable adit, tail gate auxiliary powerhouse, tail gate traffic cable tunnel, tail gate exhaust wind tunnel, leakage collecting well, underground exhaust fan room, intermediate oil tank room, etc. Grouting works and steel structure fabrication and installation works are within the scope of this construction.

Ground buildings, including the construction, decoration and outdoor civil works of the ground switch building (including the auxiliary workshop of the switch building), the guard room of the ground switch station, the wellhead room of the exhaust shaft and the diesel engine room, are also included in the scope of bidding. In addition, the design, construction, operation management, maintenance and demolition of temporary construction facilities are also included. After the completion of the

project, it will provide a strong guarantee for the safe and stable operation of the power grid in North China.

Bid winning information:

First place: Sinohydro Bureau 4 Co., Ltd.

Bid price: 28980: RMB 3,357,970,000

Second place: Sinohydro Bureau 14 Co., Ltd.

Quotation: 28959: RMB 0.3786 million

Third place: Sinohydro Bureau 8 Co., Ltd.

Tender quotation: 29279: RMB 0.58

million
All can be viewed after purchase
Correlation

Hebei Qianxi Pumped Storage Power Station is located in Luanyang Town and Shangying Town, Qianxi County, Tangshan City, Hebei Province, about 116 km away from Tangshan City and 177 km away from Beijing. The installed capacity of the power station is 1000 MW. The key project of the power station is mainly composed of the upper reservoir, the lower reservoir, the water conveyance system, the underground powerhouse and the switch station, the open channel of the river, the make-up pump station and other buildings. The upper reservoir is located at the head of the natural gully, and the terrain is relatively open. The reservoir basin is formed by excavation in the reservoir and damming of the main gully. The lower reservoir is located in the Changhe River valley. Due to the large sediment content of the river flow, in order to avoid the impact of the sediment flow on the unit, the upper reservoir is located in the Jinlongkou Village to Chaoyu Gully of the Changhe River.

2026-05-08 10:10:15

On February 13, the East China Cement Price Index was 265.51, down 0.27% from the previous month and 23.32% from the previous year. At the same time, the price of 42.5 bulk cement in Jiangsu P. O is 313-352 yuan/ton.