150MW PV! Announcement of 450MW Source-Network-Load-Storage Integration Project in Inner Mongolia

2026-09-20 17:46:06

On September 15, the Ecological Environment Bureau of Wulanchabu City, Inner Mongolia, issued a public announcement on the acceptance of the ecological environment impact assessment documents of the 450000 kilowatt source-network-load-storage integration project in Huade County, Inner Mongolia Shanhe Huatai New Energy Co., Ltd.

On

15 September, The Ecological Environment Bureau of Wulanchabu City, Inner Mongolia issued a public announcement on the acceptance of the ecological environment impact assessment documents of the 450000 kilowatt source-network-load-storage integration project in Huade County, Inner Mongolia Shanhe Huatai New Energy Co., Ltd.

150MW光伏!内蒙古450MW源网荷储一体化项目公示1

According to the announcement, the project is newly built , located in No.7 Town and Baiyintra Township, Huade County, Ulanchabu City, Inner Mongolia, and is constructed by Inner Mongolia Shanhe Huatai New Energy Co., Ltd. in two phases . The total installed capacity is 450,000 kilowatts . The total investment of the

first phase of the project is 981 million yuan , with an installed capacity of 225000 kilowatts, including 150000 kilowatts of wind power. Photovoltaic 75000 kilowatts , supporting the construction of 33.75 million kilowatts/5 hours energy storage , 220 kilovolt booster station, as well as operation management center, integrated joint operation management and control platform, collector lines, traffic engineering and other ancillary facilities; The total investment of the

second phase of the project is 911.25 million yuan , with an installed capacity of 225000 kilowatts, including 150000 kilowatts of wind power and 75000 kilowatts of photovoltaic power . Supporting the construction of 33.75 million kilowatts/5 hours of energy storage, power collection lines, traffic engineering and other ancillary facilities. The second phase of the project and the first phase of the project share one booster station, and the second phase of the project will no longer build a separate booster station, operation management center and integrated joint operation management and control platform.

This project is a source-network-load-storage integration project, with a total construction period of 17 months and a project preparation period of 1 month. The first phase of the main project is planned to start in early April 2027, and the wind turbines and photovoltaic arrays of the first phase of the project will be ready for power generation by the end of November 2027; The second phase of the project is scheduled to start construction in October 2027, and all 40 units will be put into operation by the end of July 2028. The wind power, photovoltaic field and supporting load projects of this project are constructed simultaneously.

All can be viewed after purchase
Correlation

On September 15, the Ecological Environment Bureau of Wulanchabu City, Inner Mongolia, issued a public announcement on the acceptance of the ecological environment impact assessment documents of the 450000 kilowatt source-network-load-storage integration project in Huade County, Inner Mongolia Shanhe Huatai New Energy Co., Ltd.

2026-09-20 17:46:06

In accordance with the relevant provisions of the Detailed Rules for the Implementation of the Pre-reorganisation of the Intermediate People's Court of Changchun City, Jilin Province (for Trial Implementation), during the period of pre-reorganisation, the Company and some of its subsidiaries subject to pre-reorganisation shall not pay off their debts except for the necessary expenses for the continued operation of the enterprise and the maintenance of its operating value. As at the date of this announcement, the principal and interest of overdue debts of the Company and its subsidiaries amounted to RMB6.959 billion, representing 1,124.30% of the latest audited net assets attributable to the parent company of the Company.