On June 10, 2016, at 11:18 a.m. local time in Mongolia, China Building Material International Engineering Group Corporation undertook the general contracting, and Beijing Triumph Building Material Engineering Co., Ltd. undertook the design, equipment supply and technical services. The clinker line of the second phase of Zhonglian Mongolia Cement Construction Project with an annual output of 1 million tons, which was supervised by Zhongxin Construction Consulting Company, was successfully ignited at one time according to the established plan. Sun Rongze, General Manager of Inner Mongolia Operation Area of Zhonglian Cement , Tong Guishan, Chief Engineer of Beijing Triumph Building Materials Engineering Co., Ltd., Bai Dongzhi, General Manager of Mengxin Bayingala Co., Ltd., and Wang Yehua, Acting Project Manager of Mongolia Project Department of China Building Materials International Engineering Group Co., Ltd., jointly presided over the ignition ceremony of the project. Mengxin Company, the general contractor of the project, the design unit, the supervision unit and the principal responsible persons of the construction units jointly participated in the ignition ceremony.
The successful ignition of the second phase of the Zhonglian Mongolia Project is an important node in the construction of the whole line of the Mongolia Project, which marks that the Mongolia Project will formally enter the stage of full normal production and produce high-quality cement for Mongolia, which will play a great role in promoting the local economic development. As an important project in the national "the Belt and Road" area and a pilot project of CNBM's "going out", the completion and operation of this project will become an important fulcrum of CNBM's "going out" strategy and lay a solid foundation for the Group's international development.
Since the commencement of the project construction, the once-in-a-century low temperature, cold and snowstorm weather in Mongolia has been encountered, especially this year. In March this year, the site temperature is still below minus 30 degrees, which has a great impact on the project construction progress. At the same time, this year is an election year in Mongolia, and the local political environment is relatively complex, which makes it extremely difficult for the project department to apply for a labor visa. Faced with the unfavorable factors such as the large amount of remaining project work, the shortage of project labor, the shortage of construction personnel by one third of the original plan, and the delay of the resumption time by nearly one month compared with the original plan, the project depa rtment, through the rational allocation of personnel, grasping the key lines, realizes the shift work of construction personnel, and at the same time, makes rational use of the local labor resources of Mongolia, and centers on the project. According to the goal of "one-time ignition and feeding, long-term stable operation" put forward by the owner of Zhonglian, the project was successfully ignited on schedule.
During the critical period of project construction, Chairman Song Zhiping of China Building Material Group and Chairman Peng Shou of China Building Material International Engineering Group Co., Ltd. have been concerned about and guided the project construction for many times. Other leaders of the Group, the International Department of the Group, Zhonglian Cement and leaders at all levels of China Building Material International Engineering have come to the scene to guide the project work, which has inspired everyone. It has provided many valuable opinions and support for the project construction.
The ignition of the second phase of the project on schedule fully proves that the general contracting team of the project is a team that dares to fight and can fight hard. All the staff of the project will take the successful ignition of the rotary kiln as a new starting point, and work together with the owner to complete the follow-up performance assessment and project acceptance.