On December 4, the completion ceremony of the Lafarge CHI project in India, which was contracted by Sinoma International Tianjin Company, was held. This project is the second project of cooperation between Sinoma International and Lafarge Group in India, and also the first complete production line built by Sinoma International in India, which has important demonstration significance for the company to develop the Indian market.
At the ceremony, Ujjwal. Bartria, project director of Lafarge, said in his speech that the successful commissioning of CHI project could not be separated from the high-quality service of Sinoma International Management Team, and the stable operation of the production line could not be separated from the "all-weather" professional service of Sinoma International Project Team. Through the successful implementation of the CHI project, Lafarge saw the strong strength of Sinoma International and built up confidence in Chinese equipment. The CHI project will undoubtedly become a milestone in the cooperation between Lafarge and Sinoma International, and Lafarge is looking forward to the next cooperation with Sinoma International in the Indian market.
CHI Project Site Manager Li Yougui, Commissioning Manager Cui yuanxiang and all project personnel were invited to attend the ceremony. Li Yougui and Cui yuanxiang were awarded the Outstanding Contribution Award of the Project.
Since the project was ignited in August this year, it has been running smoothly for nearly three months, and has successfully produced nearly 400,000 tons of clinker . In the "pre-assessment" work just completed, all the indicators of the production line have exceeded the contract value, which has won the high trust and recognition of the owner.
浙公网安备33010802003254号