On June 5, Ningxia Lingwu Huaxin Integrated Energy Services Co., Ltd. issued a tender announcement for EPC general contracting of Lingwu 1 GW/4 GWh centralized shared energy storage project.
Lingwu 1GW/4GWh Centralized Shared Energy Storage Project is located in Baitugang Township, Lingwu City, Ningxia Hui Autonomous Region. A 1GW/4GWh energy storage power station and a 330 booster station will be built in this project.
The 330kV line starts from the 330kV side outgoing line of Lingzhou 750kV Substation and ends at the 330kV frame of the newly-built Huaxin Energy Storage Power Station.
The planned construction period is 7 months, and the deadline for bidding is 9:00 on June 29, 2026. Consortium bidding is not accepted for
this project.