On November 10, the EPC general contracting project of Wuzhai 200 MW/400 MW H grid-side energy storage power station in Xinzhou, Shanxi, issued a tender termination announcement. The announcement shows that due to the significant changes in the implementation of the project, the bidding activities of the project will be terminated after the study and decision of the tenderer.
It is worth noting that the project was postponed twice on September 18 and September 24, 2026, respectively. The planned construction scale of the energy storage part of the project is 200 MW/400 MWh. The energy storage battery adopts lithium iron phosphate battery , and the battery system and power conversion system of the energy storage station adopt the outdoor prefabricated cabin layout scheme. The operation scheme of
the power station is proposed to have a design life of 20 years, and the battery shall be replaced once every 10 years.