"18 + X" Days! Sichuan Province's July Peak-Staggered Production Plan Released

2026-07-01 15:37:40

On July 1, Sichuan Cement Association issued the Notice on Effectively Doing a Good Job in Staggered Production in July 2026, requiring that in July 2026, the number of days of kiln shutdown for each clinker production line in staggered production is "18 + X" days.

On July 1, Sichuan Cement Association issued the Notice on Effectively Doing a Good Job in Staggered Production in July 2026, requiring that in July 2026, the number of days of kiln shutdown for each clinker production line in staggered production is "18 + X" days.

Among them, "18 days" is the baseline task, and "X days" will be organized by the Provincial Cement Association in the middle and late July to determine whether additional days are needed, depending on the factors such as the production and marketing inventory of enterprises in the whole province and the relationship between supply and demand in the market. Enterprises that still have some days in arrears before are required to make up for them in accordance with relevant regulations. Enterprises are encouraged to stop as far as possible when carrying out the monthly off-peak production tasks.

The specific task requirements are as follows:

1. In July 2026, the number of days of off-peak production and kiln shutdown for each clinker production line is "18 + X" days. Among them, "18 days" is the baseline task, and "X days" is organized by the Provincial Cement Association in the middle and late July to determine whether additional days are needed, depending on factors such as production and marketing inventory of enterprises in the province, market supply and demand, and so on. Enterprises that still have some days in arrears

before are required to make up for them in accordance with relevant regulations. Enterprises are encouraged to stop as far as possible when carrying out the monthly off-peak production tasks.

2. All cement member units are requested to fill in the plan according to the format of "Sichuan Cement Enterprises Staggered Kiln Shutdown Time Commitment", and submit the production plan for July 2026 before 17:00 on July 3, 2026. Contact: Yu Hua, Supervision Team of Sichuan Cement Association, Tel: 135 40918285.

3. Implement monthly and quarterly settlement for the completion results of peak-shifting production tasks. Verification and settlement shall be carried out monthly according to the online monitoring data of the competent department of ecological environment at the provincial level. The overfulfilled task of the current month can be used to offset the plan of the next month, and the overdue plan of the current month must be made up in the next month. The off-peak production of the quarter shall be liquidated once every quarter, and the completion of the off-peak production task can span months but not seasons.

All can be viewed after purchase
Correlation

On July 1, Sichuan Cement Association issued the Notice on Effectively Doing a Good Job in Staggered Production in July 2026, requiring that in July 2026, the number of days of kiln shutdown for each clinker production line in staggered production is "18 + X" days.

2026-07-01 15:37:40

Why the other one? Because there was a self-description of a Φ3.3m kiln cement clinker production line in January this year. The Φ3.3m kiln, which was built a few years ago and located in another city in the province, is the one I want to describe now.