year1 On May 25, the Office of Industry and Information Technology of Inner Mongolia released the Announcement on the Project of Photovoltaic Cell Packaging Materials for Solar Energy Equipment with an Annual Output of 100 Million Square Meters of Baotou Gesuolan New Energy Co., Ltd.
The announcement shows that the project plans to build three 800t/d photovoltaic rolled glass production lines . The planned ignition and production time is respectively December 2024, December 2025 and December 2026. The project is based on the technology of China Building Material Triumph Group, invested by China Nengjian, and adopts the self-developed all-oxygen electric boosting technology.
Today, The project under construction and the corresponding state-owned construction land use right of the project under construction were auctioned publicly, which means that the project has been "unfinished".
According to Digital New Energy Data.
2026, a number of photovoltaic projects have changed.
On January 24, Trina Solar announced that. No longer implement the 15GW project of the second phase of the 35 GW straightening single crystal project, and use the remaining 1.7 billion yuan raised by the second phase of the project to implement the "distributed intelligent photovoltaic power station construction project"; On the evening
of January 30, Baichuan Changyin disclosed in its performance forecast for 2025 that in order to actively respond to the challenges brought about by the cyclical adjustment of the photovoltaic industry, the company suspended its investment in the photovoltaic project of heterojunction batteries in Deqing, Zhejiang Province in 2025. At the same time , the pilot line of Shanghai heterojunction photovoltaic R & D project will be postponed;
On February 9, Mingguan New Material announced that it would terminate its investment in the construction of solar energy in Feidong County 22." Tianyang New Material said in the 2025 performance forecast that in the photovoltaic packaging ", with the photovoltaic clearing to the deep water area, many photovoltaic projects have no choice but to stop, or even no possibility of restarting. This also means that part of the government's original investment is difficult to get the expected return, so many local governments began to "collect debts".
For example, due to the long-term suspension of Yangzhou Bangjie 10GW photovoltaic cell project and the failure to resume production as planned, Bangjie shares were sued by Jiangsu Yangzhou Economic and Technological Development Zone Management Committee to the court, requiring the enterprise to return 1.
On March 7, Bangjie announced that Yangzhou Bangjie confirmed that 1.
In addition, many photovoltaic enterprises such as Yijing Optoelectronics and * ST Mubang were also asked by local governments to return their previous subsidies.