announcement of Digital New Energy DataBM shows that 34 projects are involved in this optimization. The total scale is 222. Among them
From the perspective of planned investment, the total investment of 34 projects is 96. Among them, the total investment of 12 photovoltaic projects is 2.64 billion yuan; The total investment of 22 wind power projects is 70.
This project is preferred to accept the participation of the consortium, but the number of members of the consortium shall not exceed three. After signing the consortium agreement, the parties to the consortium shall not participate in the same project optimization work in their own name, nor shall they form or participate in other consortia to participate in the same project optimization work. The
response documents are obtained from March 12, 2026 to March 16, 2026, from 8:00 to 11:30 and from 14:00 to 17:30 every day (Beijing time, excluding statutory holidays). The place of
obtaining documents is Honghe Construction Engineering Tendering Co., Ltd . The submission time of response documents for
Project 1 to Project 22 is from 8:00 to 9:00 on March 19, 2026; the deadline for submission of response documents is 9:00 on March 19, 2026. The submission time of response documents for
Project 23 to Project 34 is from 8:00 to 9:00 on March 20, 2026; the deadline for submission of response documents is 9:00 on March 20, 2026.
浙公网安备33010802003254号