Digital New Energy DataBM. Com learned that on March 13, the tender announcement for EPC project of Chongqing Fengdu 80 MW "Camellia oleifera + Photovoltaic " industrial project was issued, and the tenderer was Fengdu Sanneng New Energy Co., Ltd. The source of funds for the project is the self-raised 34789 of 0.71 million yuan .
The announcement shows that the AC side capacity of the photovoltaic area of the project is 80 MW, and the installed capacity of the DC side is about 112 MW. The bidding contents of the project include but are not limited to design consulting services, electrical equipment procurement, civil engineering, equipment installation, commissioning engineering, engineering coordination and services, etc. In terms of

performance, this tender requires bidders to start from March 1, 2021. Achievements in engineering design or construction or general contracting of photovoltaic power generation system with single capacity not less than 80 MW and above (mountain photovoltaic projects are preferred). Consortium bidding is accepted for
this project .
The project is scheduled to start in April 2026 and be connected to the grid by December 30, 2026. The time for obtaining the
bidding documents is from 9:00 on March 16, 2026 to 17:00 on March 20, 2026. The bid
closing/opening time is 9:30 on April 2, 2026.