On November 17, the termination announcement of the EPC general contracting project of the 400000 kilowatt photovoltaic project of Kecha Bingdi Fusion Rui Carbon Energy was issued. The project involves two bid sections: the 001 bid section is the EPC general contracting project. 002 bid section is EPC general contracting supervision, and both bid sections are terminated for some reasons. According to

the previous tender announcement, the tenderer of the project is Rui Carbon New Energy Co., Ltd. of Chabuchar Xibe Autonomous County, which is located in Kanxiang, Chabuchar Xibe Autonomous County, Yili, Xinjiang, covering an area of 19000 mu. The newly built photovoltaic installed capacity is 400000 kilowatts, supporting inverters , box transformers and other facilities, the total investment of the project is 130559 38000 yuan, and the planned construction period and supervision service period are 365 calendar days.
Bidding scope: the first bid section, civil construction of 400MW photovoltaic project (including infrastructure, etc.), supporting construction of inverter, box transformer and other ancillary facilities. In the second bid section, we can inspect the supervision of the EPC general contracting project of the 400000 kilowatt photovoltaic project of Rui Carbon Energy, the supervision service of the whole construction process of this project and the related services during the quality warranty period.
On June 22, the bid-winning results of the project were announced, in which the EPC general contracting of the 001 bid section was won by Shaanxi Construction Engineering Infrastructure Group Co., Ltd., with a bid rate of 98.98%; the supervision unit of the 002 bid section was Zhongxin International Project Management Co., Ltd., with a bid price of 3.530568 million yuan.
浙公网安备33010802003254号