On April 3, the EPC of the 400MW/800MWh independent energy storage power station project in the industrial accumulation area of Xiyang County, Shanxi Province, issued a tender announcement. The source of the project fund is 960 million yuan of self-raised funds, with a unit price of 1.2 yuan/Wh. The tenderer is Shanxi Shisanchu New Energy Technology Co., Ltd. The total investment of this
project is about 1.146 billion, and the main construction content is that the project capacity is 400MW/800MWh, including a 220kV booster station, a 250MVA (35kV/220kV) booster main transformer is set in the booster station, 160 sets of new energy storage units and a set of 35kV power distribution equipment.
Planned construction period: 9 months. The project accepts the consortium bidding and meets the relevant conditions.