Xinjiang Super 500 MW Photovoltaic Project EPC General Contracting Public Bidding!

2026-04-27 10:49:48

Digital New Energy DataBM. Com was informed that on April 24, the tender announcement for EPC general contracting of 700000 kilowatt photovoltaic power generation project in Karamay, Xinjiang Oilfield was issued, and the tenderer was Xinjiang Oilfield Branch of China Petroleum and Natural Gas Co., Ltd.

Digital New Energy DataBM. Com was informed that on April 24, the tender announcement for EPC general contracting of 700000 kilowatt photovoltaic power generation project in Karamay, Xinjiang Oilfield was issued. The tenderer is Xinjiang Oilfield Branch of PetroChina Company Limited.

The announcement shows that the project is located in Wuerhe District, Karamay City, Xinjiang Uygur Autonomous Region, with AC side rated capacity of 508.62 MW , DC side installed capacity of 534.052 MWp, and capacity ratio of 1: 1.05. It is planned to install 861380 N-type monocrystalline silicon double-sided double-glass photovoltaic modules of 620 peak watts and above.

Photovoltaic modules will be arranged vertically, with 2 rows and 26 columns. Each string unit consists of 52 monocrystalline double-sided modules, supporting the construction of 2333 300 kW and above string inverters and 135 3300 KVA box-type transformers.

新疆超500MW光伏项目EPC总包公开招标!1

In addition, a 70MW/140MWh (10%/2h) electrochemical energy storage system and a 50MVA synchronous condenser will be built. The bidding scope of the

project mainly includes the design of photovoltaic field, equipment procurement, civil construction of cable, grounding, box transformer foundation, installation of photovoltaic modules, box transformer, string inverter, cable, grounding and other equipment and facilities; Design, equipment procurement, civil construction and equipment installation of booster gathering station, energy storage area, synchronous condenser and ancillary facilities; commissioning, trial operation, defect elimination, training and acceptance of all equipment systems in the station area. In terms of

performance, this tender requires bidders to have at least one 100MW or above photovoltaic power generation project design and construction general contracting or design or construction general contracting performance from January 1, 2022 to the deadline for bidding. The

project contract period is from the date of signing the contract to December 31 , 2026; the construction period is from the date of signing the contract to October 30 , 2026. Consortium bidding is not accepted for

this project . The

bidding documents will be obtained from April 25 , 2026 to April 29 , 2026.

The bid deadline and bid opening time is 8:30 on May 18, 2026.

All can be viewed after purchase
Correlation

Digital New Energy DataBM. Com was informed that on April 24, the tender announcement for EPC general contracting of 700000 kilowatt photovoltaic power generation project in Karamay, Xinjiang Oilfield was issued, and the tenderer was Xinjiang Oilfield Branch of China Petroleum and Natural Gas Co., Ltd.

2026-04-27 10:49:48

Among them, "15 days" is the baseline task, and "X days" is organized by the Provincial Cement Association in the middle and late May to determine whether additional days are needed, depending on factors such as production and marketing inventory of enterprises in the province, market supply and demand, etc.