On August 20, Inner Mongolia Daqin New Energy Technology Co., Ltd. issued a tender announcement for 300 MW/1200 MWh independent new energy storage project (EPC).
The project will build a new energy storage power station with a capacity of 300 MW/1200 MWh lithium iron phosphate electrochemical energy storage system and a supporting 220 kV booster station. A new 220kV line is connected to the 220kV side of Huangheshao 500kV Substation. The project investment is 1.08 billion yuan, equivalent to 0.9 yuan/Wh. The project is located in Huangheshao Town, Saihan District, Hohhot, Inner Mongolia. The project is
required to be completed before December 30, 2026. Consortium bidding is not allowed for this project. The deadline for bidding is 09:00 on September 14, 2026.