On August 28, Shandong Energy Bureau issued the "Notice on Issuing the List of Centralized Photovoltaic Power Generation Projects in 2026 (the second batch)". A total of 20 centralized photovoltaic power generation projects were involved , with an installed capacity of 183.
The project promises to be completed and put into operation before 2027. For projects that fail to be connected to the grid at full capacity during the promised period, they will be removed from the construction list and linked to the follow-up project declaration of the enterprise. The corresponding increase of " project construction units in the city involves Datang, China Energy Conservation, Huaneng, China Power Construction, Huadian, Three Gorges, China Guangdong Nuclear Power and other energy central enterprises.
Among them, Datang involves three projects with a total capacity of 444 MW , CECEP involves three projects with a total capacity of 325 MW , and Huaneng involves two projects. Capacity : 250MW . In January
this year, the Energy Bureau of Shandong Province issued the List of Centralized Photovoltaic Power Generation Projects in 2026 (the first batch), which includes 29 projects with a capacity of 297
. Huaneng, < a href = "https://www.databm.".