EPC Bidding for Guangzhou 150MW PV Project!

2026-01-27 11:51:38

Digital New Energy DataBM. Com was informed that on January 23, Guangzhou Development Chongqing Xiushan Photovoltaic Project EPC General Contracting Tender Announcement was issued, and the tender unit was Guangzhou Development New Energy Group Co., Ltd.

Digital New Energy DataBM. Com was informed that on January 23, Guangzhou Development Chongqing Xiushan Photovoltaic Project EPC General Contracting Tender Announcement was issued, and the tender unit was Guangzhou Development New Energy Group Co., Ltd.

The announcement shows that the project is located in Xiushan Tujia and Miao Autonomous County of Chongqing, and the installed capacity of photovoltaic AC side is planned to be 150 MW . 331,205 N-type 620Wp monocrystalline double-sided PV modules are planned to be installed in the whole site , with a total of 65 power generation units and 468 320 kW string inverters . A new 110kV booster station is planned to be built in the

project. The photovoltaic array is connected to the new 110kV booster station of the project by 9 circuits of 35kV collector lines. The generated power is sent to the 110kV side of Xiushan Substation by 1 circuit of 110kV line after being boosted by the collector line through the main transformer. The new overhead line is about 12.3 km long.

The bidding scope includes the general contracting work of the whole process of project commencement ceremony, effect drawing and construction process record display, project formalities, government coordination, engineering survey and design, equipment and material procurement and supply, etc.

The project is scheduled to complete full capacity grid connection by December 31, 2026.

This tender requires the bidder to have at least one grid-connected EPC general contracting project with a single capacity of 100MWp or above from January 1, 2021 to the deadline for bidding. Consortium bidding is accepted

in this tender . Only a consortium composed of no more than 2 units shall be accepted, with 1 member of the consortium undertaking the design task and 1 member of the consortium undertaking the construction task, and the agreement shall be signed. The bid

closing/opening time is 9:00 on February 13, 2026.

All can be viewed after purchase
Correlation

Digital New Energy DataBM. Com was informed that on January 23, Guangzhou Development Chongqing Xiushan Photovoltaic Project EPC General Contracting Tender Announcement was issued, and the tender unit was Guangzhou Development New Energy Group Co., Ltd.

2026-01-27 11:51:38

This project starts from Kuitun East (about 2km east of Changjiang Road Interchange of G30 Lianhuo Expressway), connects with the existing Lianhuo Expressway, and ends at Kuqa East (about 2.5km east of Kuqa Toll Station of G3012 Tuhe Expressway). According to the existing Tuhe Expressway, the total length is 393.693 km. Section KDK-TJSG-1starts from about 2.3km east of the existing Changjiang Road Interchange of Lianhuo Expressway, with the starting chainage of K27 + 000 and the ending chainage of K113 + 192, and the total length of the route is 83.045km. Bid section KDK-TJSG-2 is connected to the end of contract section DKSGTSJ-2, and the starting point of the route is at K of Kuitun River