On May 26, Core Energy Technology announced that. The company intends to terminate the " , one of the projects to issue convertible corporate bonds to non-specific targets in 2023. Core Energy Technology plans to terminate 15 distributed photovoltaic power station projects this time, with a registered installed capacity of 77.
The project has undergone 2 adjustments and 2 extensions . In March
2023, Core Energy Technology issued convertible bonds to raise funds .
Among them, the total investment in the construction of distributed photovoltaic power plants was 723 million yuan .
According to the announcement at that time, Core Energy Technology plans to build distributed photovoltaic power plants on the roofs of industrial and commercial enterprises in Zhejiang, Jiangsu, Guangdong, Hubei, Anhui and Tianjin. The total number of projects is 55 , the total scale is 166.26 MW , the construction period is 12 months, and the average annual power generation is expected to be about 15,740.
2023. After the adjustment of PV ", the total scale of the above distributed PV power plant projects increased to 204.31 MW . The total investment amount was increased to 7.
The adjustment proposal was considered and approved by the board of directors and the general meeting of shareholders of Core Energy Technology in December 2023.
Ten months later, on October 25, 2024, the company announced that the implementation period of the distributed photovoltaic power plant construction project would be extended to October 2025, on the grounds that the owner's roof resources could not be delivered in time due to the impact of the industry environment and industrial policies.
Replace with the new distributed power station project reserved by the company. The comparison before and after the adjustment is as follows:
As of May 19, 2026, 62 of the above 77 investment projects have been connected to the grid, with a record installed capacity of 136.03 MW. The actual installed capacity is 134. In addition, there are 15 projects that have not been built, and the registered installed capacity is 77.