"The strength of the bottom concrete layer has reached 0.32 Mpa, and the sliding work can be carried out." At the construction site of the project of Shaanxi-Chongqing Building Materials Company with an annual output of 5 million tons of sand and gravel aggregates, with an order, the Jack of the finished aggregate silo was lifted by one stroke. So far

"The strength of the bottom concrete layer has reached 0.32 Mpa, and the sliding work can be carried out." At the construction site of the project of Shaanxi-Chongqing Building Materials Company with an annual output of 5 million tons of sand and gravel aggregates, with an order, the Jack of the finished aggregate silo was lifted by one stroke. Up to now, the No.3 warehouse has not stopped working for 46 hours. Since the smooth opening of the finished aggregate silo on July 8, the No.4 and No.5 silos have been sliding to the top smoothly.

In midsummer July, the heat wave hit people, Chongqing as a senior "furnace" city, the high temperature continued to "dominate the screen". More than 200 construction workers, under the scorching sun and without fear of "baking", shuttled through every corner of the construction site, composing a labor hymn of anti-high temperature and anti-heat. Cable trench foundation is backfilled on the first floor of the

central control building, brick wall masonry on the second floor, structural column formwork; column steel bar binding and plane beam steel bar binding are erected in the finished screening workshop; the foundation of the crushing workshop is replaced and tamped. The project construction site is in full swing and in good order. The roar of vehicles, the sound of machine operation and the command of technicians are interwoven, playing the song of project construction.

"In order to cope with the high temperature, we have worked out a construction plan for heatstroke prevention and cooling, carried out emergency drills for heatstroke and training for various production safety accidents, equipped rescue teams, arranged full-time personnel to focus on supervising the implementation of the high temperature plan, and prepared heatstroke prevention medicines, sunscreen products and cooling herbal tea to avoid heatstroke for workers." The company's on-site director said.

The company carefully optimizes the construction plan and refines the decomposition work. During the construction process, we should constantly strengthen the site safety and quality inspection, start with every detail, strictly control the construction quality, and eliminate potential safety hazards. At the same time, overall coordination ensures that each link is closely linked and operates efficiently. Reverse schedule, wall chart operations, under the premise of resolutely ensuring construction safety and quality, open the "night" rush mode, and make every effort to pull the "progress bar" of the project. With

the scorching sun and stars as companions, all participants in the project will take more firm responsibility, more full enthusiasm for work, more pragmatic work style, fight against the heat, interpret responsibility and responsibility with sweat, strive to be the first, seize the day and seize the night, and strive to sprint towards the goal.

All can be viewed after purchase
Correlation

"The strength of the bottom concrete layer has reached 0.32 Mpa, and the sliding work can be carried out." At the construction site of the project of Shaanxi-Chongqing Building Materials Company with an annual output of 5 million tons of sand and gravel aggregates, with an order, the Jack of the finished aggregate silo was lifted by one stroke. So far

2024-07-29 11:04:50

Villagers Fu Mou-mou and Li Mou-mou provided assistance for illegal sand mining activities, identified as accomplices in illegal sand mining, sentenced to one year, three months and eight months'imprisonment respectively, and fined 3000 yuan and 2000 yuan respectively.

2023-07-20 10:56:03

This measure solves the problem that it is inconvenient to add lining plates to the inner walls of irregular and arc-shaped guide grooves and feed inlets for anti-wear protection, and also greatly reduces the labor cost and production cost.

2023-06-05 09:23:43

The daily production capacity can reach 3000 cubic meters, supplying concrete engineering materials for each mixing station in the pipeline.

2023-05-23 09:20:29

Driven by the resumption of production, the market demand for sand and gravel in Chengdu has also warmed up.

2023-03-10 17:46:12

Jidong Equipment disclosed its 2022 annual performance forecast, during which the company's net profit is expected to be 11.6 million yuan to 15 million yuan, down 28.33% to 44.57% from the same period last year.

2023-01-10 09:32:54

Prices in Ningxia are stable but export sales are low, Gansu is facing callback pressure after price increases, sales in Qinghai are not up to expectations after pushing up, Shaanxi has great resistance to price recovery, Xinjiang is stable due to engineering demand, and the overall market is mainly stable price wait-and-see in the short term.