On October 28, the successful candidate of 100MW centralized photovoltaic power generation project in Meijiang Town, Lanxi City, Zhejiang Province was announced. There are three shortlisted candidates, namely:
China Railway Wuhan Electrification Bureau Group Co., Ltd.; Jiangxi Electric Power Design Institute Co., Ltd. of China Power Construction Group, with a unit price of 3.171 yuan/watt;
Zhejiang Jie'an Engineering Co., Ltd.; Lanxi Hongye Construction Co., Ltd.; The bidding unit price of Zhejiang Electric Power Design Institute Co., Ltd. of China Energy Engineering Group is 3.176 yuan/watt;
the bidding unit price of Zhongji Guoneng Zhejiang Engineering Co., Ltd. and Zhejiang Urban Construction Gas Thermal Power Design Institute Co., Ltd. is 3.176 yuan/watt.

Previously, on September 26, the tender announcement for the above project was issued.
The tender announcement shows that the planned capacity of the project is 100 MW (AC side) , and the actual installed capacity is about 126. 26208 MWp (DC side) . It adopts the mode of block generation and centralized grid connection, and consists of 15 2. 7 MW (the maximum DC side can be connected to 3. 42342 MWp) and 18 3. 3 MW (the maximum DC side can be connected to 4. 18418 MWp) power generation units, which are connected to the 35 kV distribution room of the new 110 kV booster station through 4 35 kV collector lines after boosting. The bidding estimate is 457,501,854 yuan .
This tender adopts the "turnkey" general contracting mode, covering pre-formalities, survey and design, equipment procurement and installation, construction, commissioning, acceptance and handover, and warranty services.