From December 1 to 2, Datang Group successively announced the successful candidates for Fujian Fuan Xiwei 80 MW Photovoltaic EPC General Contracting Project and Chongqing Tongliang District Shanxin 50 MW Photovoltaic EPC General Contracting Project (second time).
Datang Fujian Fuan Xiwei 80 MW Fishery Complementary Photovoltaic Power Station New Project EPC General Contracting Project has been shortlisted for two candidates, both of which are consortia. The winning unit price is 1.946 yuan/ watt and 2.013 yuan/ watt respectively.

On November 5, the tender announcement was issued for the project, and the tenderer was Fujian Datang International Ningde Power Generation Co., Ltd. The project is located in Xiapi Village, Xiwei Town, Fuan City, Ningde, with a construction scale of 80MW and a planned construction period from March 1, 2026 to March 31, 2027.
The bidding scope includes: EPC general contracting engineering survey, design and optimization design, procurement of equipment and materials (except for those supplied by Party A), construction and installation, standardization of safety facilities (including seven brands and two drawings), test and inspection, system commissioning, trial operation, engineering defect elimination, etc. Two candidates were selected for the EPC general contracting (secondary) project of Shanxin 50 MW Agricultural Photovoltaic Power Generation New Project in Tongliang District, Chongqing
, Datang. The winning unit price is 2.423 yuan/ watt and 2.567 yuan/ watt respectively.

On November 4, the tender announcement was issued for the project, and the tenderer was Yuneng (Group) Co., Ltd. The project is located in Pulu Street, Tongliang District, Chongqing, with a construction scale of 49.92 MW and a planned construction period from December 30, 2025 to May 30, 2026.
The bidding scope includes: preliminary design of the project (or feasibility study optimization), survey and design of construction drawings and preparation of as-built drawings, procurement of all equipment and materials by the bidder, supply, unloading and storage, secondary transportation, construction and defect elimination. Photovoltaic power plant, booster station, road, five links and one leveling, test pile, slope protection, drainage facilities and other construction and installation works, as well as the implementation of environmental and water conservation measures.