The new Bomi-Ranwu railway project won the bid.

2025-12-16 10:38:25

The successful bidding of the new Bomi-Ranwu Railway Project marks new progress in the construction of the Sichuan-Xizang Railway Corridor and will effectively enhance the traffic capacity of the eastern part of the Xizang.

Name of

Project: New Bomi-Ranwu Railway Station Project

Construction Location: Bomi-Ranwu, Bomi County, Nyingchi Prefecture, Xizang Autonomous

Construction Scale: The line starts from Jianbomi Station and ends at Ranwu Station, Basu County, Changdu City, with a total length of 134.5 km. The ratio of bridge to tunnel is 83. There are 7 new stations along the whole line and 5 open stations in the initial stage.

Bidding scope: from Bomi Station (excluded) to Ranwu Station (included), the newly-built main line is 134.19km long; Bomi Station of Bomi-Ranwu Railway is introduced into the relief line project, with a line length of 2.26km; 3. The scope of this tender is the pre-station works within the design scope of the above construction drawings (excluding ballastless track laying and ballasted track works). Division of

bid sections: This tender is divided into 3 bid sections, with bid section numbers of BRZQ-1, BRZQ-2, BRZQ-3

and BRZQ-1. The project quantities are as follows: (1) Main line: 6.5 tunnels with a 26970 of 63 m, 10 bridges with a 11250 of 2 m, 11 sections with a subgrade 10728 of 86 m, and 2 stations; (2) Connecting line in Lhasa direction: 1 bridge with a length of 2120.21 m; (3) Connecting line in Chengdu direction: 2 bridges with a length of 3152.1m; (4) Bomi East Dangerous Goods Line: 813.75 m/2 section of subgrade, bridge 401., mileage/scope: Bomi Station (excluded) ~ No.1 transverse tunnel work area of Songzong Tunnel.

BRZQ-2, main line: 2 tunnels of 28452 of 0.31m, 5 bridges of 4116.93m, subgrade

of 6392.BRZQ-3, Quantities of works: (1) Main line: 2.5 tunnels (42635.74m), 4 bridges (1116.25m), subgrade 2551., mileage/scope: work area of No.3 transverse tunnel of Zaen Tunnel ~ Ranwu Station (included).

Bid winning information:

BRZQ-1

First place: China Railway No.4 Engineering Group Co., Ltd.

Bid price after evaluation (RMB): 4758316764

Second place: China Railway No.12 Engineering Group Co., Ltd.

Evaluated bid price (RMB): 4758354887

No.3: China Railway No.8 Engineering Group Co., Ltd.

Evaluated bid price (RMB): 4758653137

BRZQ-2

First place: CCCC Second Highway Engineering Co., Ltd.

Evaluated bid price (RMB): 3470302790

Second place: China Railway 14th Bureau Group Co., Ltd.

Evaluated bid price (RMB): 3470313131

No.3: China Railway 17th Bureau Group Co., Ltd.

Evaluated bid price (RMB): 3470356814

BRZQ-3

First place: China Railway 20th Bureau Group Co., Ltd.

Bid price evaluated (RMB): 5369921574

Second place: CCCC Second Harbor Engineering Co., Ltd.

Evaluated bid price (RMB): 5369961099

No.3: China Railway 19th Bureau Group Co., Ltd

. Evaluated bid price (RMB): Name of 5370030561

: Newly-built Bomi-Ranwu Railway Construction Power Supply Project

Construction Location: Bomi-Ranwu, Bomi County, Nyingchi Prefecture, Xizang Autonomous

Construction Scale: The line starts from Jianbomi Station and ends at Ranwu Station, Basu County, Changdu City. The total length is 134.5 kilometers, and the ratio of bridge to tunnel is 83. Seven new stations will be built along the whole line, and five stations will be opened in the initial stage.

Bidding scope: from Bomi Station (excluding) to Ranwu Station (including), the new main line is 134.19 km long; Bomi Station of Bomi-Ranwu Railway is introduced into the relief line project, with a line length of 2.26 km; the new upstream and downstream connecting lines in Chengdu direction are built, with a line length of 3. The bidding scope is the construction of power supply works within the above scope.

BRGD-1, project quantity: 1 110kV power line, 140.3km 35kV power supply trunk line, branch line 52. Mileage/scope: Bomi Station (excluded) to Ranwu Station (included).

Bid winning information:

First place: China Railway Electrification Bureau Group Co., Ltd.

Bid price (RMB): 170247861

Second place: China Railway 11th Bureau Group Electrical Engineering Co., Ltd

. Bid price (RMB): 170249367

No.3: China Railway Construction Electrification Bureau Group Southern Engineering Co., Ltd.

Bid Price (RMB): 170247944

Project Name: Construction Site of New Bomi-Ranwu Railway Station Works and Construction Power Supply Works

Construction scale from Bomi to Ranwu

, Bomi County, Nyingchi Prefecture, Xizang Autonomous: The line starts from Bomi Station and ends at Ranwu Station, Basu County, Changdu City, with a total length of 134.5 kilometers. The ratio of bridge to tunnel is 83. Seven new stations will be built along the line, and five stations will be opened in the initial stage.

Bidding scope: from Bomi Station (excluded) to Ranwu Station (included), the newly-built main line is 134.19km long; Bomi Station of Bomi-Ranwu Railway is introduced into the relief line project, with a line length of 2.26km; 3. The scope of this tender is the construction supervision of pre-station works (excluding ballastless track laying and ballasted track works) and construction power supply within the scope of the above construction drawing design. The

division of bid sections is divided into 3 bid sections, and the conditions of each bid section are as follows: BRZQJL-1, BRZQJL-2, BRZQJL-3,

BRZQJL-1, and the quantities of works are as follows: (1) Main line: 26970 of tunnel: 63m/6.5, 11250 of bridge:.2m/10, subgrade 10728: 86m/11, 2 stations; (2) connecting line in Lhasa direction: bridge: 2120.21m/1; (3) connecting line in Chengdu direction: bridge: 3152.1m/2; (4) Bomi East Dangerous Goods Line: 813.75 m/2 section of subgrade, bridge 401. Mileage/scope: Bomi Station (excluded) ~ No.1 transverse tunnel work area of Songzong Tunnel.

BRZQJL-2, the project quantities are: (1) Main line: 2 tunnels with 28452 of 0.31 m, 5 bridges with a total length of 4116.93 m, and subgrade of 6392. (2) One 110 kV power line, and 140.3 km of 35 kV power supply trunk line. Branch line 52. Mileage/scope: exit work area of Songzong Tunnel ~ No.1 transverse tunnel work area of Zaen Tunnel New Bomi-Ranwu Railway Construction Power Supply Project.

BRZQJL-3, the project quantity is: (1) Main line: 2.5 tunnels with a 42635 of 74m, 4 bridges with a length of 1116.25m, and a subgrade of 2551. Mileage/scope: work area of No.3 transverse tunnel of Zaen Tunnel to Ranwu Station (included).

All can be viewed after purchase
Correlation

The successful bidding of the new Bomi-Ranwu Railway Project marks new progress in the construction of the Sichuan-Xizang Railway Corridor and will effectively enhance the traffic capacity of the eastern part of the Xizang.

2025-12-16 10:38:25

Several China Railway Engineering Bureaus have won the bid for major projects, demonstrating their strong competitiveness and leading position in the field of infrastructure construction.

2025-11-12 16:33:08

More vigilance is that capacity replenishment is essentially a reinvestment behavior, for cement enterprises, as soon as possible to recover investment costs is the core demand, which means that the probability of enterprises will significantly increase capacity utilization next year. For enterprises with no overproduction space and no capacity to supplement, they can only produce in strict accordance with the approved capacity. It is difficult to reconcile the uneven and "unfair" contradictions at the operational level, which will further aggravate the instability of the cement market next year. It can be predicted that after this round of supplementary production, a new round of market competition in the cement industry will begin.