Terminate! Reject the bid! Change of over 250 MW PV EPC project

2026-04-20 09:07:35

On April 13, the announcement of bid rejection of the design and construction general contracting (EPC) of the "Agricultural Photovoltaic Complementary" Photovoltaic Cooperation Project in Kaili City was issued. Due to the major adjustment of the construction scale and implementation content of the project, it is now decided to terminate the relevant bidding activities of the project, so the bid of the project is rejected.

On April 16, the first batch of distributed photovoltaic power generation EPC projects of Yunnan Tuo Nuclear Energy Technology (Yunnan) Co., Ltd. in 2026 were terminated because the construction unit could not fulfill the construction contract .

终止!废标!超250MW光伏EPC项目生变1

It is noteworthy that this is not the first time that the project has been terminated. As early as February 8, the project was terminated due to major changes. On the day of termination (February 8), the tenderer of the project, Tuo Nuclear Energy Technology (Yunnan) Co., Ltd. , immediately re-issued the tender announcement.

The project is divided into one bid section, using crystalline silicon photovoltaic modules , leasing the roof of the park, installing photovoltaic equipment, with a tentative total installed capacity of 50 MW (DC side) , using self-generation and self-use, and the surplus electricity is connected to the grid.

Then on March 12, the tenderer of the project issued the announcement of the result of winning the bid. Finally, TBEA Xinjiang New Energy Co., Ltd. won the bid with a total quotation of 10000 yuan 12250 and an average unit price of 2.45 yuan/W .

But only one month later, the project failed again. Coincidentally

.

On April 13, the announcement of the abandoned bid for the design and construction of the " Agricultural Photovoltaic Complementary " Photovoltaic Cooperative Project in Kaili City was issued, due to the major adjustment of the project construction scale and implementation content. Now it is decided to terminate the relevant bidding activities of this project, so the bid of this project is rejected.

终止!废标!超250MW光伏EPC项目生变2

Previous bidding information shows that the project is located in Kaili City, Qiandongnan Miao and Dong Autonomous Prefecture, Guizhou Province. The tenderer can invest in Ledian New Energy (Kaili) Co., Ltd. to develop distributed photovoltaic projects in Baiwu Street Duck Farm, Bibo Town Shihua Village, Baiwu Street Fertilizer Plant, Gandong Division of Sankeshu Town (Xiaogechong), Baiwu Street Beef Cattle Breeding Base and Qinglong Village of Zhouxi Town. The total development capacity of the project is 203.77 MW , including 46.02 MW of 1.5 million meat duck breeding demonstration base in Baiwu Street, Kaili City, 50.81 MW of Shihua Village base in Bibo Town, Kaili City, and 5.97 MW of chemical fertilizer plant demonstration base in Kaili City. Gandongshi (Xiaogechong) Breeding Base, Sankeshu Town, Kaili City, 40.01MW; High-quality Beef Cattle Industry Demonstration Base, Kaili City, 33.07MW; Edible Fungus Base, Qinglong Village, Zhouxi Town, Kaili City, 27.89MW.

This project adopts the fixed total price method of EPC general contracting, and the bidding scope includes the installation of photovoltaic brackets, component inverters , grid-connected combiner boxes, step-up transformers and other equipment on the site provided by the construction unit. To realize the design, material and equipment procurement, construction, commissioning, acceptance and related coordination services required for operation included in the construction scale of the project.

The project is developed in batches, and the planned construction period is full capacity grid-connected and put into operation within 4 months after receiving the written commencement documents from the tenderee. The original bid opening time of the

project is 10:30 a.m. on April 16, 2026.

All can be viewed after purchase
Correlation

On October 10, the Bureau of Ecology and Environment of Aba Prefecture, Sichuan Province, issued a public announcement on the acceptance of the EIA documents for the photovoltaic power generation project of Chishajiao (Phase II) in Maoxian County, Aba Prefecture. According to the announcement, the project is located in Wadi Town and Shaba Town, Maoxian County, Aba Prefecture, Sichuan Province, with a total investment of 63088 8600 yuan.

2026-10-20 18:10:31

On October 19, according to foreign media reports, Swift Current Energy, an independent power producer, filed a lawsuit against First Solar, an American solar module manufacturer.

2026-10-20 17:54:41

DBM Data: List of Proposed PV Power Station Projects Last Week (Filing) (10.12-10.18)

2026-10-20 15:08:35

On October 16, the Bureau of Ecology and Environment of Ganzi Prefecture, Sichuan Province, issued an announcement on the acceptance of the ecological environmental impact assessment documents for the construction projects of Daofu Gehapu Phase I 500MW Photovoltaic Project and Daofu Gonglu Phase II 1.3 MW Photovoltaic Project.

2026-10-20 11:33:33

List of Proposed Photovoltaic Power Station Projects Last Week (10.12-10.18)

2026-10-20 10:31:21

Longji Green Energy and ENGIE reached 800MW photovoltaic + 500 MWh energy storage framework cooperation to accelerate the landing of overseas clean energy projects.

2026-10-20 09:26:19

On October 16, the official website of the Management Committee of Yangzhou Economic and Technological Development Zone of Jiangsu Province announced the approval opinions on the EIA documents of "Jingao Yangzhou R & D No.1 Solar Cell Technology Research and Development Project" and "Jingao Yangzhou Base Battery Technology Renovation Project".

2026-10-19 17:09:21

On October 15, Jiangsu Huadian Changzhou Wujin Qianhuanglingtai 219 MW Fishing-photovoltaic Complementary Photovoltaic Project EPC general contracting successful candidates were announced.

2026-10-19 10:55:15

On October 16, the Bureau of Ecology and Environment of Ganzi Prefecture, Sichuan Province, issued an announcement on the acceptance of the ecological environmental impact assessment documents for the construction projects of Daofu Gehapu Phase I 500MW Photovoltaic Project and Daofu Gonglu Phase II 1.3 MW Photovoltaic Project.

2026-10-19 10:29:38

On October 15, Jiangsu Huadian Changzhou Wujin Qianhuanglingtai 219 MW Fishing-photovoltaic Complementary Photovoltaic Project EPC general contracting successful candidates were announced.

2026-10-19 09:17:05

On October 9, the Bureau of Ecological Environment of Southwest Guizhou issued the "Announcement on the Acceptance of the Report Form on the Ecological Environmental Impact of Leye Agricultural Photovoltaic Power Station (Major Changes) in Wangmo County".

2026-10-19 09:16:40

On October 10, the Ecological Environment Bureau of Nanling County, Wuhu City, Anhui Province released the full version of the ecological environment impact report form of the 100MW fishing-photovoltaic complementary power generation project in Kuihu, Xuzhen, Nanling County.

2026-10-19 09:15:50

On October 14, the Bureau of Ecology and Environment of Qijiang District of Chongqing issued a public announcement on the acceptance of the EIA report of Qijiang Longsheng Photovoltaic Project.

2026-10-19 09:14:26

According to the incomplete statistics of digital new energy DataBM. Com, the capacity of photovoltaic module collection and calibration and entry projects announced in two weeks (10.3-10.16) is about 2.81 GW, which is 35.4% lower than that of the previous period (9.19-10.2) 4.35 GW; At the same time, the total amount of bidding projects for photovoltaic modules is about 6.60 GW, which is more than 14 times higher than 0.41 GW in the previous period.

2026-10-19 09:12:09

On October 15, the People's Government of Xiangshui County, Yancheng City, Jiangsu Province issued the Announcement on the Stability Evaluation of the Decision-making Matters of the 300 MW Centralized Photovoltaic Project of Xinghai New Energy Co., Ltd. in Xiangshui County.

2026-10-17 10:30:19

According to the incomplete statistics of the digital new energy DataBM. Com, from October 5, 2026 to October 11, 2026, there are 21 EPC general contracting projects for photovoltaic power plants in China, as well as DB general contracting, optical storage integrated general contracting and other general contracting projects, involving a project scale of 0.693 GW, with a total winning amount of 1.711 billion yuan. ......

2026-10-16 16:32:30

According to the incomplete statistics of the digital new energy DataBM. Com, from September 28, 2026 to October 4, 2026, there are 32 EPC general contracting projects for photovoltaic power plants in China, as well as DB general contracting, optical storage integrated general contracting and other general contracting projects, involving a project scale of 1.913 GW, with a total winning amount of 4.775 billion yuan. ......

2026-10-16 16:08:10

On October 8, the Bureau of Ecology and Environment of Chuxiong Prefecture, Yunnan Province, issued a public announcement on the proposed review of the environmental impact assessment documents for the photovoltaic power generation project of Auricularia auricula.

2026-10-16 13:38:02

On September 16, Fumin County, Kunming, Yunnan Province, held a 2026 investment promotion docking meeting for the green energy industry chain. Fumin County Development and Reform Bureau has signed four investment invitation agreements with China Energy Construction, Huaneng Xiongfei, Yibin New Energy and China Coal Southwest Branch respectively.

2026-10-16 11:17:13

The total investment is about 130 million yuan, mainly for the construction of 40 MW photovoltaic field and a 220 kV booster station. It is planned to use single crystal double-sided photovoltaic modules with a single capacity of 615 Wp.

2026-10-15 10:14:21

On September 16, Fumin County, Kunming City, Yunnan Province, held the 2026 investment promotion docking meeting of the green energy industry chain.

2026-10-15 10:13:00

On October 9, the ecological environment impact report form of CNNC Yangshan 300 MW Agricultural Photovoltaic Complementary Project (second re-approval) was publicized before approval.

2026-10-15 10:01:21

On October 9, the Ecological Environment Bureau of Southwest Guizhou accepted the ecological environment impact assessment document of Sanglang Agricultural Photovoltaic Power Station (major changes) in Wangmo County.

2026-10-14 17:36:18

On October 12, Xinjiang Changji Hutubi 400MW Photovoltaic Project EPC General Contracting Project (Bid Section II: 250MW Photovoltaic) was tendered.

2026-10-14 16:30:54

It is reported that the project is the first "photovoltaic + energy storage" integrated project of the total energy-saving solar energy company in the Xizang.

2026-10-13 18:12:17

DBM Data: List of Proposed PV Power Station Projects Last Week (Filing) (10.5-10.11)

2026-10-13 16:20:47

On October 12, Xinjiang Changji Hutubi 400MW Photovoltaic Project EPC General Contracting Project (Bid Section II: 250MW Photovoltaic) was tendered.

2026-10-13 09:59:27

On October 3, Hunan Leiyang Yuqing 90 MW Linguang Complementary Photovoltaic Power Generation Project was officially started.

2026-10-13 09:22:47

Recently, the three major photovoltaic sand control projects of Huadian, Huaneng and CGN in Inner Mongolia have been approved successively, with a total investment of over 8.3 billion yuan and an installed capacity of 3.5G W.

2026-10-12 15:08:18

On October 9, Gansu Energy announced that Lu Jiqing had applied to resign as chairman, director and convenor of the Strategic and Sustainable Development Committee for reasons of job adjustment. After his resignation, Lu Jiqing will not hold any other positions in the company and its holding subsidiaries.

2026-10-12 11:58:36

On October 9, China Water Conservancy and Hydropower Fifth Engineering Bureau Co., Ltd., a subsidiary of China Electric Power Construction, disclosed that the 300000 kilowatt photovoltaic composite project in Futula, Lingwu City, Ningxia, was officially started.

2026-10-12 09:12:52

On October 9, China Water Conservancy and Hydropower Fifth Engineering Bureau Co., Ltd., a subsidiary of China Electric Power Construction, disclosed that the 300000 kilowatt photovoltaic composite project in Futula, Lingwu City, Ningxia, was officially started. 

2026-10-10 17:30:33

Wenchang Business Environment Construction Bureau said that the project is a centralized photovoltaic project, and the Bureau has no right to accept and file. The window staff of the Bureau did not strictly check the authority of centralized photovoltaic power generation project filing, and exceeded their authority to examine and approve the project filing for the Department, which was beyond the statutory authority.

2026-10-10 13:09:16

The pace of photovoltaic project construction is accelerating.

2026-10-10 11:55:04

On October 8, Shaanxi Development and Reform Commission issued the Announcement on Decentralized Wind Power and Small Ground Photovoltaic Power Station Projects in Shaanxi Province in 2026.

2026-10-10 10:30:29

On the evening of October 9, Yunnan Energy Investment announced that in order to firmly grasp the strategic development opportunities and promote the company's new energy business to become stronger, better and bigger, Huaping Yunneng New Energy Co., Ltd. was agreed to invest in the construction of hot spring photovoltaic power generation projects (Lijiang) and red deer photovoltaic power generation projects.

2026-10-10 09:29:41

On October 8, Shaanxi Development and Reform Commission issued the Announcement on Decentralized Wind Power and Small Ground Photovoltaic Power Station Projects in Shaanxi Province in 2026.

2026-10-09 17:37:52

On October 8, Shanxi Energy Bureau issued the announcement on the scale list (supplement) of the third batch of wind power and photovoltaic power generation projects to be abolished in 2026. It is proposed to abolish 8 wind and solar projects with a total scale of 458,300 kW reported by Lvliang and Changzhi, including 6 photovoltaic projects with a scale of 358.3 MW and 2 wind power projects with a scale of 100 MW.

2026-10-09 16:30:57

DBM Data: List of Proposed PV Power Station Projects Last Week (Filing) (9.28-10.4)

2026-10-09 13:39:19

DBM Data: List of Proposed PV Power Station Projects Last Week (Filing) (9.21-9.27)

2026-10-09 13:32:00

On September 30, the Iraqi DCC second-line 6000t/d clinker cement production line and supporting 50 MW photovoltaic project contracted by Suzhou Sinoma EPC successfully obtained the FAC certificate issued by the owner DELTA Group, marking the successful achievement of all contract objectives such as project construction implementation, full-line performance assessment and closed-loop management of defect liability period. Complete performance and formal and comprehensive handover of the project.

2026-10-09 11:45:02

A total of 86 wind power and photovoltaic power generation projects (to be) abolished

2026-10-09 10:15:37

On September 30, the website of Jiangyin Municipal People's Government of Jiangsu Province issued the announcement of the proposed approval of the ecological environment impact report form of the fishing-photovoltaic complementary photovoltaic power generation project (re-approval) of Jiangyin Huangtuli Port of the State Power Investment Corporation.

2026-10-09 09:30:39

The installed capacity of the project is 108.2MW 31604 at the DC side and 99.2MW at the AC side. 655Wp monocrystalline silicon modules are used, and the total quantity is 65368 blocks.

2026-10-09 09:29:58

Previously, the project was included in the list of guaranteed grid-connected projects of wind power and photovoltaic power generation in Shanxi Province in 2024.

2026-10-09 09:23:41

List of Proposed Photovoltaic Power Station Projects Last Week (09.28-10.04)

2026-10-08 10:59:12

Jiangning Development Zone Government Affairs Service Center on Huaneng Jiangning Lukou Street (Phase II) 45MW Fishery Complementary Photovoltaic Power Generation Project Ecological Environment Impact Assessment Document to be reviewed and publicized

2026-10-08 10:36:18

On September 29, Shanxi Energy Bureau announced the list of the third batch of wind power and photovoltaic power generation projects to be abolished in 2026, and proposed to abolish 17 projects with a scale of 1.517 million kilowatts (1.517 GW), such as Datang Huike Xinghualing 100MW wind power.

2026-09-30 16:02:43

China Electric Power Construction Henan Company said that due to multiple factors such as pre-formalities and site preparation, the project started four months behind the original plan.

2026-09-30 16:00:54

The implementation list of this experimental project has a scale of 5.5 million kilowatts, totaling five projects, with a sand control task area of 220000 mu. The main body of the project involves CGN, China Electric Power Construction, Huadian Group and Huaneng Group.

2026-09-30 15:57:47

On October 13, the Office of Industry and Information Technology of Jiangxi Province announced that due to the revision of the policy of capacity replacement in the cement and glass industry by the Ministry of Industry and Information Technology, the Office of Industry and Information Technology of Jiangxi Province decided to abolish the Rules for the Implementation of Capacity Replacement in the Cement and Glass Industry of Jiangxi Province (Gongxin Regulation No.2024) from the date of issuance of the notice, and to abolish the "Rules for the Implementation of Capacity Replacement in the Cement and Glass Industry of Jiangxi Province". The capacity replacement of cement and glass industry in the whole province will be handled in accordance with the relevant policies of the Ministry of Industry and Information Technology in the future.