on September 27, the 120 MW photovoltaic power generation project of Qingxiangshu (Phase II) in Shuangbai County, Datang County, Yunnan Province officially held a commencement ceremony and entered the critical stage of construction. The
project was previously launched by Datang Group in March 2026, and Henan Engineering Co., Ltd. of China Electric Power Construction Group won the bid with 69.505 million yuan. Affected by the pre-formalities, site preparation and other factors, the project started four months behind the original plan. The original planned construction period is from May 6 to November 30, 2026.