On November 20, Saifutian announced that its holding subsidiary, Anhui Meidal un Photovoltaic Technology , had a contract dispute over the first phase EPC project of its 10g W new high-efficiency solar cell intelligent factory. In Mingguang People's Court, he sued China United Engineering Co., Ltd. and Anhui Huiming Construction Group for a total of 91.2284 million yuan in liquidated damages for overdue completion.
Saifutian has two major production bases in Mingguang, Anhui and Xuzhou, Jiangsu. Among them, the 10GW TOPCon battery factory project is located in Mingguang Jingkai District, Mingguang City, Anhui Province, with a total investment of 8 billion yuan and two phases of construction. The first phase was officially put into operation on November 7, 2023. The project was originally agreed to be fully completed on August 31, 2023, but the overall completion acceptance has not yet been completed. At present, the court has accepted the case and has not yet opened a court session.