, 2026, the Bureau of Ecology and Environment of Xinzhou City, Shanxi Province, issued an administrative penalty decision to punish Datang yuanping Clean Energy Co., Ltd. After investigation, the company's Datang yuanping 70 MW photovoltaic power generation project 220kV outgoing line started construction in April 2024 and was connected to the grid with full capacity in May 2025. Among them, the act of building without approval will not be punished because it exceeds the two-year limitation of accountability; After the implementation of the Eco-environmental Code on August 15, 2026, the law enforcement departments, in accordance with the principle of "from the old to the light", compared with the old and new editions of Shanxi Province's eco-environmental administrative penalty discretion benchmark, applied the lighter penalty benchmark of August 2026, and imposed a fine of 216000 yuan on enterprises. It is required to complete the rectification and submit a written report by December 6, 2026.