DBM Video: 3 Vendors Cut Prices! The scope of price reduction has been expanded again.

2026-10-29 17:06:04

Old friends, there is movement again this week. In the first half of the week, three leading manufacturers lowered the price of components. Not many manufacturers have adjusted their prices this time, but the scope of price reduction has obviously expanded.

Old friends, there is movement again this week. In the first half of the week, three leading manufacturers lowered the price of components . Not many manufacturers have adjusted their prices this time, but the scope of price reduction has obviously expanded. Look at the decline

first. 645 to 655 watts of high-efficiency products, the transaction has dropped to 0.72 to 0.74 yuan per watt; the rest of the mainstream products, further down to 0.69 to 0.71 yuan per watt. According to the

model. The quotation of TOPCon components is stable and loose at the end of the transaction. Jinko, Tianhe, Tongwei three head manufacturers distributed channel turnover dropped 1 to 4 cents, the head mainstream turnover dropped 1 to 2 cents from last week, to 0.66 to 0.75 yuan per watt, the second and third lines stabilized at 0.64 to 0.69 yuan per watt.

BC is relatively stable, and the transaction price of head high-efficiency components has not changed. However, at the end of the year, distributors hoarded goods in batches again, and the price of goods was low. This part was concentrated in 650 to 655 watts, and the terminal transaction reached 0.77 to 0.78 yuan per watt, which was 2 to 3 cents lower than last week.

HJT is stable as a whole, the scale of low-price products is expanding, the distribution channels of 720 to 730 watts can be booked in large quantities, and the price has not gone down for the time being, maintaining at about 0.67 to 0.68 yuan per watt.

Looking back on the first half of the week, the number of price cuts is not large, the scope of price cuts for mainstream specifications is expanded, and the weight is different. In fact, the supply side has already given a response-some manufacturers plan to sharply reduce production scheduling in November, with the obvious intention of reducing the price; of course, there are also a few who go against the trend and raise the price, grabbing the share of others. But the price is not enough to rely on the supply side alone, the key is to see the demand: the end of the year this wave of rush to install, maybe it will end ahead of schedule. If demand continues to weaken, it will be useless for manufacturers to cut production, and prices will still have to go down.

On the one hand, the supply is being collected, and on the other hand, the demand is not improving. What does this round of quotation depend on? Talk in the comments section. See you next time!

In the first half of the week, the digital new energy DataBM. Com investigated and learned the price information as follows:

TOPCon components: the price range is 0.65-0.75 yuan/W.

BC component: the price range is 0.74-0.88 yuan/W.

HJT module: the price range is 0.67-0.76 yuan/W.

The above survey price is the price including tax and excluding transportation.


All can be viewed after purchase
Correlation

On October 28, Wulanchabu Jingda 1500MW "Wind, Solar, Fire and Storage Integration" large-scale wind power photovoltaic base project was officially started in Fengzhen City, Wulanchabu City, Inner Mongolia.

2026-10-30 10:30:30

On October 23, Nigeria's Economic and Financial Crimes Commission (EFCC) launched an operation in Ogray, Ogun State, to destroy four lithium ore processing plants suspected of illegal operation, and arrested 15 suspects, including 14 Chinese citizens and one Nigerian.

2026-10-29 17:27:21

Old friends, there is movement again this week. In the first half of the week, three leading manufacturers lowered the price of components. Not many manufacturers have adjusted their prices this time, but the scope of price reduction has obviously expanded.

2026-10-29 17:06:04

On October 27, the Three Gorges Group issued a tender announcement for centralized procurement of photovoltaic modules, photovoltaic inverters and photovoltaic brackets (the first batch) in 2027. The total procurement capacity of the three types of equipment is about 19.9 GW, and the bid opening time is November 17.

2026-10-29 16:30:11

On October 26, Ningde Times Energy Storage Technology Co., Ltd. was established in Ningde, Fujian Province, with a registered capital of 5 billion yuan. It is wholly owned by Ningde Times New Energy Technology Co., Ltd. and its legal representative is Dai Xingwei. According to public information, Dai Xingwei is the Minister of Post-Investment Management of Ningde Times.

2026-10-29 13:37:34

On October 28, Longyuan Electric Power issued the announcement of the change of the first batch of public bidding projects for the procurement of photovoltaic module equipment framework in 2026.

2026-10-29 10:30:07

On October 26, Enjie shares disclosed the third quarter report of 2026. In the first three quarters, the Company realized an operating income of RMB14.226 billion, representing a year-on-year increase of 49.07%; the net profit attributable to the parent company was RMB1.794 billion, representing a loss of RMB86.323 million in the same period of last year, turning losses into profits.

2026-10-28 17:01:33

On October 27, the second phase of the 100MW fishing-photovoltaic complementary photovoltaic power station project in Dongwu Area of the North Bank Economic Development Zone of SDIC Power was officially started.

2026-10-28 16:46:01

Recently, Yajiang (Qiongjie) New Energy Co., Ltd. was registered in Qiongjie County, the Shannan Prefecture of Lhasa City of Xizang, with a registered capital of 100 million yuan. The company is wholly owned by China Yajiang Group New Energy Co., Ltd., both of which belong to China Yajiang Group, a central enterprise.

2026-10-28 15:15:24

On the morning of October 22, Yuecheng District and Binhai New Area of Shaoxing City, Zhejiang Province held a major investment project docking activity, and Xiexin Photovoltaic Perovskite Photovoltaic Module Industrialization Project was formally signed.

2026-10-28 11:03:51

Recently, Ningde Times signed a memorandum of understanding with INTILION, a European energy storage solution provider, to supply 3 gigawatt hours of energy storage systems in the next five years. These systems will focus on supporting grid-level and commercial energy storage projects in Germany, Switzerland and Austria.

2026-10-28 10:54:59

On October 25, the tender announcement for EPC general contracting of two grid-side independent energy storage projects in Laiwu District, Jinan, Shandong Province was issued simultaneously, with a total scale of 600 MW/1200 MWh and a total investment of 1.44 billion yuan.

2026-10-27 16:50:07

Recently, Tian Eye Check industrial and commercial information shows that Master Kang (Chongqing) Convenient Food Co., Ltd. has undergone industrial and commercial changes, including new power generation business, transmission business, power supply (distribution) business, and photovoltaic power generation equipment leasing.

2026-10-27 16:06:46

On October 23, two new energy projects in Suining, Sichuan, were launched simultaneously. Sichuan Huiqiang New Material Wet Diaphragm Project with an annual output of 2.8 billion square meters has a total investment of 2 billion yuan. Eight new wet diaphragms and 30 coating production lines have been built. 60% of the field leveling has been completed. Trial production is planned for August 2027. Huiqiang New Material is the core supplier of Ningde Times and BYD.

2026-10-27 15:00:17

On the evening of October 26, Penghui Energy released its report for the third quarter of 2026. In the first three quarters, the net profit attributable to the parent company increased by 928.81% year-on-year, and the operating income was 17.866 billion yuan, an increase of 135.67% year-on-year. The net profit attributable to shareholders of listed companies was 1.178 billion yuan, an increase of 928.81% year-on-year; Net profit after deducting non-recurring gains and losses was 1.202 billion yuan, up 7545.71% year on year.

2026-10-27 11:08:45

From October 19 to 21, the Bureau of Ecology and Environment of Wanzhou District of Chongqing issued a public announcement on the acceptance of environmental impact assessment of two major photovoltaic projects.

2026-10-27 11:03:19

On the evening of October 23, Jingao Science and Technology announced that the board of directors had considered and approved the Bill on Terminating the Implementation of the Employee Stock Ownership Plan in 2025, and the supporting management measures were terminated simultaneously.

2026-10-26 16:38:28

On October 24, Jiangsu Xiyuan Group announced the successful candidates for the 500 MW/2 GWh independent energy storage project in Hainan, Qinghai.

2026-10-26 15:23:11

On the evening of October 24, Rongbai Science and Technology announced that it planned to invest about 3.603 billion yuan to build an integrated project with an annual output of 200000 tons of sodium cathode materials in Xiangyang, Hubei Province. The construction period is expected to be 12 months, and construction is expected to start in November 2026.

2026-10-26 11:42:42

On October 21, Anhui Jianghuai Automobile Group Co., Ltd. Zunjie Super Factory Distributed Photovoltaic Power Generation and Energy Storage Construction Project Photovoltaic Power Station EPC Project (second) bidding results were announced.

2026-10-26 10:49:41

On October 16, Chongqing Tongnan District Ecological Environment Bureau issued a public announcement on the acceptance of the EIA documents of "Chongqing Huadian Tongnan Mixin Composite Photovoltaic Power Generation Project" and "Chongqing Huadian Tongnan Yuxi Composite Photovoltaic Power Generation Project".

2026-10-25 10:30:58

On October 21, the tender announcement for the general contracting of the centralized photovoltaic power generation project (secondary) in Wusu City, Tacheng District, Xinjiang was issued.

2026-10-24 14:30:10

On October 15, the Bureau of Ecology and Environment of Nanjing City, Jiangsu Province, issued a public announcement on the acceptance of the EIA documents for the 100m W ground centralized photovoltaic power generation project in Huaneng Zero Carbon Park. The project is located in Hongfeng Block and Xinhe Village Block, Qixia Street, Qixia District, Nanjing City, with a total investment of 500 million yuan and a construction period of 12 months for a photovoltaic power station with a total installed capacity of 100MW.

2026-10-23 16:30:07

On October 21, Tesla disclosed its third quarter earnings in 2026. Overall revenue was flat at $28.05 billion, while net profit was down 43% at $787 million.

2026-10-23 11:02:30

On October 21, due to the change of bidding content, the EPC general contract of 200MW household distributed photovoltaic project in Ningxia was terminated.

2026-10-23 10:30:31

Lao Tie, the line-ups of component price reduction has been expanded again. Last week, eight manufacturers cut prices, and two second and third lines were added in the first half of the week, with a drop of 2 to 3 points. However, in the first half of the week, the head quotation is still stable for the time being.

2026-10-22 17:16:09

On October 20, the announcement was issued before the implementation of the procurement of energy storage system equipment for the 250 MW/1000 MWh independent energy storage project in Hohhot, Inner Mongolia.

2026-10-22 16:49:52

On the evening of October 21, Aixu announced that it planned to invest 1.150 billion yuan to upgrade the existing PERC battery capacity of Tianjin Base to 6GWABC battery capacity. The project is scheduled to start in the fourth quarter of 2026 and put into operation in the third quarter of 2027.

2026-10-22 16:30:08

On October 20, Tianqi Lithium disclosed its performance forecast, predicting to achieve net profit of 5.1 billion yuan to 6 billion yuan in the first three quarters of 2026, with a year-on-year increase of 2734.97% to 3235.26%; net profit after deduction of non-profits of 5.03 billion yuan to 5.93 billion yuan, with a year-on-year increase of 6957.09% to 8219.79%.

2026-10-22 14:50:15

On October 21, Shanshan issued a fixed increase plan announcement, intending to issue a shares to indirect controlling shareholder Conch Group, raising a total of no more than 4 billion yuan.

2026-10-22 11:00:14

On October 20, Guizhou Energy Bureau announced that 22 wind power and photovoltaic power generation projects were approved for filing from July 2026 to September 2026, with a total scale of 2.3875 million kilowatts.

2026-10-22 10:30:00

Recently, the 200MW/800MWh independent new energy storage EPC project in Wusu City, Xinjiang issued a tender termination announcement. The original bid opening time of the project was October 21. The reason for the termination was that the project had undergone major changes.

2026-10-21 16:45:16

On October 15, the Natural Resources Bureau of Lingwu City, Ningxia, issued an administrative penalty decision to a photovoltaic power generation company in Ningxia, which implemented a 35 KV collector line project in four villages of Majiatan Town, Ningxia, suspected of illegal occupation of grasslands, dry farmland, woodland, and land vegetation damage caused by vehicle rolling. He was fined a total of 0.09 yuan 996305.

2026-10-21 16:30:58

On the evening of October 20, Sunshine Power and Xinwangda announced that they would co-invest with professional investment institutions to set up a partnership to establish Shenzhen yuanzhi Juxin Shengrong Energy Storage Asset Private Equity Fund Partnership (Limited Partnership) with a total subscription of 1 billion yuan.

2026-10-21 15:14:03

On the evening of October 20, Ningde Times released its third quarter report for 2026. In the third quarter, the company realized revenue of 165.221 billion yuan, an increase of 58.58% over the previous year, and realized net profit of 21.246 billion yuan attributable to shareholders of listed companies, an increase of 14.54% over the previous year.

2026-10-21 11:06:42

On October 10, the Bureau of Ecology and Environment of Aba Prefecture, Sichuan Province, issued a public announcement on the acceptance of the EIA documents for the photovoltaic power generation project of Chishajiao (Phase II) in Maoxian County, Aba Prefecture.

2026-10-21 10:30:37

On October 19, Huawei's smart car solutions subsidiary was expected to formally sign a strategic cooperation framework agreement with Ningde Times and Times Electric Service. The three parties will focus on the ecological construction of intelligent power exchange and create a new experience of senseless energy supplement for the era of automatic driving.

2026-10-20 15:32:19

On October 19, Xiexin Technologies announced that it intends to acquire about 81.91% of its controlling stake in Sichuan Xiexin Lithium Electricity Technology Co., Ltd. from the controlling shareholder Xiexin Group at a price not less than HK $1.3 per share, with an initial consideration of about 2.5 billion yuan.

2026-10-20 14:53:51

On October 16, the Bureau of Ecology and Environment of Ganzi Prefecture, Sichuan Province, issued an announcement on the acceptance of the ecological environmental impact assessment documents for the construction projects of Daofu Gehapu Phase I 500MW Photovoltaic Project and Daofu Gonglu Phase II 1.3 MW Photovoltaic Project.

2026-10-20 11:33:33

On October 16, Jiangxi Ganzhou Nankang District Light Storage and Charging Clean Energy Integration Construction Project was tendered, with a construction and installation cost of about 474 million yuan. The tenderer, Ganzhou Nankang District Hongbo Commerce and Trade Co., Ltd., is a state-owned enterprise.

2026-10-20 11:05:21

On October 16, the official website of Yangzhou Economic and Technological Development Zone issued two announcements to approve the EIA documents of "Jingao Yangzhou R & D No.1 Solar Cell Technology Research and Development Project" and "Jingao Yangzhou Base Battery Technology Renovation Project" of Jingao (Yangzhou) Solar Energy Technology Co., Ltd.

2026-10-19 17:00:50

On October 19, the National Energy Administration reported the handling of complaints and reports on the energy regulatory hotline in September 2026. Among them, people in Yinchuan, Ningxia reported through the 12398 hotline that there were hidden dangers in the quality of a centralized energy storage power station project invested by an electric power enterprise.

2026-10-19 15:24:00

On October 15, Yiwei Lithium Energy announced that the company expects a net profit of 5.068 billion yuan to 5.350 billion yuan attributable to shareholders of listed companies in the first three quarters of 2026, an increase of 80% to 90% over the same period last year; Net profit after deducting recurring gains and losses was 3.875 billion yuan to 4.262 billion yuan, an increase of 100% to 120% over the same period of last year, and the growth rate of deducting non-profits was even more prominent. At the same time, it is expected that business income in the first three quarters will increase by about 60% year-on-year.

2026-10-19 11:06:49

On October 15, Jiangsu Huadian Changzhou Wujin Qianhuanglingtai 219 MW Fishing-photovoltaic Complementary Photovoltaic Project EPC general contracting successful candidates were announced.

2026-10-19 10:55:15

On October 15, the People's Government of Xiangshui County, Yancheng City, Jiangsu Province issued the Announcement on the Stability Evaluation of the Decision-making Matters of the 300 MW Centralized Photovoltaic Project of Xinghai New Energy Co., Ltd. in Xiangshui County.

2026-10-17 10:30:19

On October 13, Guodian Electric Power Inner Mongolia Comprehensive Energy Guodian Electric Power "Mengdian into Anhui" New Energy Base Overall Implementation Plan and Feasibility Study Report Compilation Service Public Bidding.

2026-10-16 16:21:29

On September 16, Fumin County, Kunming, Yunnan Province, held a 2026 investment promotion docking meeting for the green energy industry chain. Fumin County Development and Reform Bureau has signed four investment invitation agreements with China Energy Construction, Huaneng Xiongfei, Yibin New Energy and China Coal Southwest Branch respectively.

2026-10-16 11:17:13

Operating income in the third quarter was RMB13.062 billion, representing a year-on-year increase of 109.03%; net profit attributable to parent company was RMB755 million, representing a year-on-year increase of 35.62%.

2026-10-16 09:50:27

Old iron, just after the National Day holiday, the component market has ushered in a wave of adjustment-six manufacturers have lowered their quotations, the overall decline of 1 to 3 points, and this wave of price reduction is not over yet. Recently, the demand of overseas component market has not met expectations, the distributed market continues to be depressed, the shipment of component manufacturers is mainly supported by domestic centralized projects, the inventory has been relatively high, from the supply and demand point of view, the price of components can not find support at present.

2026-10-15 17:10:30

On October 13, Inner Mongolia Lvneng Chuangyan Qingshuihe County 600 MW/2400 MWh Independent Energy Storage Project EPC started bidding, the tenderer is Lvneng Chuangyan Investment and Development (Guangxi) Co., Ltd., the total investment of the project is about 2.4 billion yuan, equivalent to EPC unit price of about 1 yuan/Wh.

2026-10-15 16:48:18

On the 29th, major enterprises in eastern Guangdong, such as Meizhou, Shanwei and Chaozhou, tried again to raise cement prices by 10-15 yuan/ton. The specific implementation needs further follow-up and observation.