On June 22, Beijing Guohua Jianglai Science and Technology Group Co., Ltd. announced that the first successful candidate was Shaanxi Chemical Construction Engineering Co., Ltd. The bid price is 2.575 billion yuan and the unit price is 2.575 yuan/watt.
The project is located in Minfeng County, Hetian, Xinjiang, with AC side scale of 1000MW, DC side installed capacity of about 1300MW, a new 220kV booster station and a sand control area of 30,000 mu.
This bidding project is divided into one bid section, which is a turnkey project. The construction period is 18 months, and it is planned to start on June 30, 2026 and complete on December 30, 2027.