20, Foster issued a " Notice on the Extension of Some Fundraising and Investment Projects", intending to invest in two photovoltaic film projects and one photovoltaic power generation project under the company. As well as the extension of the construction period of one photosensitive dry film project, including
the "annual output of 250 million square meters of high-efficiency battery packaging film project" and the "annual output of 210 million square meters of photosensitive dry film project" to be extended to December 2027; The construction period of
"annual output of 250 million square meters of photovoltaic film project" and "3855.04 KWp roof distributed photovoltaic power generation project" is planned to be extended to December 2028.

Foster said that in the first three quarters of this year, the start-up rate of downstream components was low, the supply and demand of the film market was loose, the utilization rate of industry capacity was under pressure, and the industry was in the stage of capacity digestion. Based on the principle of giving priority to capacity efficiency, the company took the initiative to slow down the pace of new capacity delivery, and gave priority to undertaking existing orders through technological transformation of stock production lines and optimization of production rate, so as to avoid idle new capacity. The project simultaneously carries out equipment selection optimization and flexible transformation of production lines to improve the return on investment per unit capacity.
At the same time, Foster said that based on the principle of prudence, combined with the actual progress of the current project, the construction period of the four projects will be extended without any change in the main body of the project, the use of the raised funds and the scale of the investment.
Up to now, the " 250 million square meters per year high-efficiency battery packaging film project " located at Hangzhou headquarters in Zhejiang Province has completed about 70% of the capacity construction. The remaining capacity will be put into operation in 2027; The "photovoltaic film project with an annual output of 250 million square meters"
in Jiangmen, Guangdong, has completed part of the plant and supporting construction , and has not yet formed effective production capacity, and the company will continue to track changes in downstream demand. Dynamic promotion of project construction, matching the rhythm of industry demand, is expected to complete production capacity by December 2028.
"3855.04KWp Roof Distributed Photovoltaic Power Generation Project" is mainly an energy project supporting "Jiangmen Film Project", and its construction period will be carried out according to the construction situation of "Jiangmen Film Project". Therefore, the construction period of this project will be extended to December 2028 simultaneously with "Jiangmen Film Project".
In addition, the "annual output of 210 million square meters of photosensitive dry film project" is the first time that the company has built a large-scale electronic material production base outside the headquarters. At present, the installation and commissioning of some production lines have been completed and trial production has been carried out. The remaining capacity will be completed and put into operation in 2027.